Install The Router Using A Lift - Juniper MX960 Quick Start Manual

3d universal edge router
Hide thumbs Also See for MX960:
Table of Contents

Advertisement

MX960 3D Universal Edge Router Quick Start

Install the Router Using a Lift

10
Before installing the router, you must remove the following components:
Power supplies
Switch Control Boards (SCBs)
Cable management system
Routing Engines
Air filter
Fan trays
Line cards:
Dense Port Concentrators (DPCs)
Flexible PIC Concentrators (FPCs)
Physical Interface Cards (PICs)
Modular Port Concentrators (MPCs)
Modular Interface Cards (MICs)
To remove the components from the router:
Slide each component out of the chassis evenly so that it does not become stuck or
1.
damaged.
Label each component as you remove it so you can reinstall it in the correct location.
2.
Immediately store each removed component in an electrostatic bag.
3.
Do not stack removed components. Lay each one on a flat surface.
4.
NOTE:
For complete instructions on removing router components, see the
MX960 3D Universal Edge Router Hardware Guide.
Before installing the router, you must remove all components (see
on page
9). To install the router using a lift:
Ensure that the rack is in its permanent location and is secured to the building. Ensure
1.
that the installation site allows adequate clearance for both airflow and maintenance.
For details, see the MX960 3D Universal Edge Router Hardware Guide.
Load the router onto the lift, making sure it rests securely on the lift platform (see
2.
Figure 6 on page
11).
"Remove Components"
Copyright © 2015, Juniper Networks, Inc.