Preparing for installation

Installation overview

Introduction
This section provides an overview of the steps required to install the 1002rp
server and peripheral devices.

Installation checklist

The following checklist identifies the tasks that must be performed when
installing the CallPilot server. For detailed instructions, see Chapter 5,
"Installing the server." When you are finished with the installation, continue
with the Installation and Configuration Task List (555-7101-210).
Step
Description
1
Ensure that you have reviewed the "Installing the CallPilot
server" section in the Installation and Configuration Task List
(555-7101-210), and completed stage 1 of the "Installation
checklist."
2
Unpack the server, and ensure you have all the items you need
(see page 37).
Complete the following checklists that are provided in the
Installation and Configuration Task List (555-7101-210):
"CallPilot software media and documentation checklist"
"CallPilot server hardware checklist"
3
Remove the front bezel and server cover, and inspect the
interior (see pages 39 and 42).
4
Replace the server cover.
5
Install the power supply modules in the server (see page 47).
34