Placing the boiler

4
Placing the boiler
This chapter describes how to install and place the boiler
in the boiler room.
Caution: Risk of system damage due to
freezing.
V Install the heating system in a frost-free
room.
4.1

Wall clearances

Wherever possible, position the boiler with the recom-
mended wall clearances. Reducing the minimum clear-
ances makes the boiler more difficult to access.
The boiler base or foundation must be perfectly flat and
level.
The burner door is factory-fitted with the hinges on the
right. The burner door can be converted to left hand
closing.
Dimen-
sion
Wall clearance
A
Recommended
minimum
B
Recommended
minimum
C
Recommended
minimum
D
Recommended
minimum
L
Chapter 2.6.1, page 10
Tab. 9 Recommended and minimum wall clearances
(dimensions in inches)
The boilers are designed for a side clearance
of 6 ".
Where applicable, allow extra wall clearanc-
es for additional components such as DHW
tank pipe connections, flue silencer, other
flue components, etc.
Warning: Risk of fire from flammable materi-
als or liquids.
V Clearances less than 6" must comply with
local and statutory codes.
V Make sure that there is a sufficient clear-
ance between combustible materials and
the chimney connection as specified by
NFPA 31 (distance of 18 ").
V The floor must comply with the require-
ments of NFPA 31.
16
Logano GB125 BE US/CA - Technical specifications are subject to change without prior notice.
40"
27"
27"
16"
28"
20"
16"
Fig. 8
6"
Wall clearances in the boiler room (boiler posi-
tioned on the right-hand side)

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Logano gb125/35 beLogano gb125/30 be

Table of Contents