Lifting And Carrying The Boiler; Placing The Boiler; Clearances; Leveling The Boiler - Buderus Logano GC 124 II Installation And Service Instructions Manual

Gas boiler
Hide thumbs Also See for Logano GC 124 II:
Table of Contents

Advertisement

▶ Secure boiler on the boiler cart.
▶ Move boiler to desired location.
▶ Place the boiler at its final postion.
5.2

Lifting and carrying the boiler

The boiler can be picked up at the both long sides of the boiler as shown.
CAUTION: Risk of injury due to carrying heavy loads.
▶ Lift and carry the boiler with at least four people at the
designated side panel locations.
Fig. 6 Lifting and carrying the boiler
6

Placing the boiler

This chapter explains how to place the boiler and position it in the boiler
room.
NOTICE: System damage due to frost.
▶ Place the boiler in a frost-free room.
The boiler is very heavy when filled with water. Check that the floor can
bear the weight before installation.
6.1

Clearances

The GC124 boiler is approved for closet installation. The following
minimum distances must then be maintained:
• front: 2",
• sides: 2",
• behind open draft hood: 6",
• above boiler top panel: 30".
A space of at least 33 inches is recommended in front of the boiler with
the door removed to allow sufficient access space for operation and
maintenance. When the door is closed, a minimum clearance of 2 inches
is required at the front and sides, 2 inches clearance is also required for
the flue pipe and 30 inches clearance to the ceiling. The installation
location and the base must be smooth and horizontal.The boiler may be
installed on a flammable base, but not on carpet.
Logano GC 124 II – 6 720 804 440 (2012/11)
Fig. 7 Required clearances in the boiler room
[1]
Recommended service clearances
[2]
Required minimum clearances
[3]
Burner tray access door with combustion air opening as required
per ANSI Z.223.1
6.2

Leveling the boiler

Level the boiler in both horizontal directions.
▶ Level the boiler using a level and place small wedges (not supplied) for
leveling purposes.
6 720 804 440-06.1T
7

Boiler installation

This chapter describes how to install the boiler. This includes the
following tasks:
• Connecting the heating system
• Electrical connection
• Gas supply piping connection
7.1

Preparing for installation

▶ Unpack all boxes and containers and check all parts against the
packing lists to make sure that everything has been supplied.
Placing the boiler
Every boiler is carefully inspected and tested before it
leaves the factory. However, if you discover any damage
or missing parts, please inform your supplier
immediately. Before disposing of packing material,
make sure that no parts are still in it.
For better access remove the front door.
6
1
2
3
6 720 804 440-07.1T