Termination Heights For Vents Above Flat Or Sloped Roofs - Vermont Castings KHLDV400PTSCSB Installation And Operating Instructions Manual

Khldv series direct vent gas fireplace
Table of Contents

Advertisement

KHLDV Series Gas Fireplace
/
1
1 0
Nails
Figure 25 - If Area Above is Not a Room, Install
Firestop above Framed Hole as Shown
2. Assemble the desired lengths of pipe and elbows nec-
essary to reach from the burner system fl ue up through
the fi restop. Be sure pipe and elbow connections are
fully twist-locked.
3. Cut a hole in the roof using the locating hole as a center
point. (Cover any exposed open vent pipes before
cutting hole in roof). The 10
hole must be measured on the horizontal. Actual length
may be larger depending on the pitch of the roof. There
must be a 1" minimum clearance from the vent pipe to
combustible materials. (Insulation should be considered
a combustible material).
4. Connect a section of pipe and extend up through the
hole.
Horizontal Overhang
2 ft.
Min.
Termination Vent
Storm Collar
Flashing
Concentric
Vent Pipe
Figure 26 -
Minimum Chimney Clearance
20
1 0
"
1
2
/
"
2
Firestop
1
1/ 2
/
"x10
" (267 x 267 mm)
2
Vertical Wall
2 ft. Min.
Lowest
Discharge
Opening
H*
X
1" Minimum
Clearances to
Combustibles
NOTE: If an offset is needed to avoid obstructions, you
must support the vent pipe every three (3) feet. Use wall
straps for this purpose. Refer to Page 18, Figure 21.
Whenever possible, use 45° elbows instead of 90° elbows.
The 45° elbow offers less restriction to the fl ow of the fl ue
gases and intake air.
5. Place the fl ashing over the pipe section(s) extending
through the roof. Secure the base of the fl ashing to
the roof and framing with roofi ng nails. Be sure roofi ng
material overlaps the top edge of the fl ashing. There
must be a 1" clearance from the vent pipe to combustible
materials.
FP1970
6. Continue to add pipe sections until the height of the vent
cap meets the minimum building code requirements.
NOTE: You must increase vent height for steep roof
pitches. Nearby trees, adjoining roof lines, steep pitched
roofs, and other similar factors may cause poor draft or
down-drafting in high winds. Increasing the vent height
may solve this problem.
NOTE: If the vent pipe passes through any occupied areas
above the fi rst fl oor, including storage spaces and closets,
you must enclose pipe. You may frame and sheetrock the
enclosure with standard construction material. Make sure
to meet the minimum allowable clearances to combustibles.
Do not fi ll any of the required clearance spaces with
insulation.
TERMINATION HEIGHTS FOR VENTS ABOVE
FLAT OR SLOPED ROOFS
Over 6/12 to 7/12
Over 7/12 to 8/12
Over 8/12 to 9/12
Over 9/12 to 10/12
Over 10/12 to 11/12
Over 11/12 to 12/12
12
*H - Minimum height from roof to lowest discharge opening
of vent
VENTING INSTALLATION
Roof Pitch
Flat to 6/12
H (feet)
1.0
1.25
1.5
2.0
2.5
3.25
4.0
20306742