Commissioning steps CGG-1K
1)
Gasart
2)
Calculated flue length
Integral flue gas butterfly orifice plate
3)
Gas supply pressure checked?
4)
Nozzle pressures checked?
(only complete when changing the gas type):
5)
Gas leak test carried out?
6)
Balanced flue system checked?
7)
Water connections checked for leaks?
8)
Vented boiler and system?
9)
System pressure 1.5 - 2.5 bar?
10)
Function test carried out?
11)
Casing fitted?
12)
System user trained, tech. docs. handed over?
13)
Commissioning confirmed?
Company / Name
Date / Signature
3062087_1108

Commissioning report

Natural gas H
LPG
Wobbe-Index____________________kWh/m³
Calorific value_________________kWh/m³
_______________________________________ m
No.____________________ /_______________ mm
______________________________________ mbar
________________________________________
______________ / _________________________