Commissioning Report - Wolf CGB-75 Instructions Manual

Wall mounted boiler conversion to other gas types
Table of Contents

Advertisement

Available languages
  • EN

Available languages

  • ENGLISH, page 61
Commissioning steps
1.) Gas type
2.) Gas supply pressure checked?
3.) Gas leak test carried out?
4.) Balanced flue system checked?
5.) Water connections checked for leaks?
6.) Fill the siphon
7.) Boiler and system vented?
8.) System pressure 1.5 - 2.5 bar?
9.) Entered gas type and output onto label?
10.) Function test carried out?
11.) Flue gas test:
Flue gas temperature gross
Intake air temperature
Flue gas temperature net
Carbon dioxide content (CO
Carbon monoxide content (CO)
12.) Casing fitted?
13.) System user trained, documentation handed over?
14.) Confirm commissioning?
3061741_201712.indd

Commissioning report

) or oxygen content (O
2
2
Test value or confirmation
Natural gas E/H
LPG
Wobbe index
Net calorific value
)
kWh/m³
kWh/m³
t
[°C]
A
t
[°C]
L
(t
- t
) [°C]
A
L
%
ppm