Initial Gas Line Preparation
1. Prepare the drip leg for furnace
connection. NOTE: Do not
attach the right side back
spacer yet to allow enough
space for tightening these
fittings.
IMPORTANT: Ensure all code and gas line sizing requirements are followed!
All connections should be properly tightened and sealed with pipe dope or Teflon tape.
ATTACHING THE GAS CONNECTION (Part 1)
2. Attach the drip leg to the
furnace. Use two wrenches to
prevent damage to the furnace.
3. If using appliance flex
gas line (recommended),
attach flair adaptor to the
drip leg. NOTE: The
connection of the
flexible gas line will be
covered in a following
procedure.