Heatilator ECLIPSE-32 Installation Manual
Hide thumbs Also See for ECLIPSE-32:
Table of Contents

Advertisement

Quick Links

INSTALLER: Leave this manual with party responsible for use and operation.
OWNER: Retain this manual for future reference.
Contact your dealer with questions regarding installation, operation or service.
NOTICE: DO NOT discard this manual!
Models:
This appliance may be installed as an OEM
installation in manufactured home (USA
only) or mobile home and must be installed
in accordance with the manufacturer's
instructions and the Manufactured Home
Construction and Safety Standard, Title 24
CFR, Part 3280 in the United States, or the
Standard for Installation in Mobile Homes,
CAN/CSA Z240 MH Series, in Canada.
This appliance is only for use with the type(s)
of gas indicated on the rating plate. This
appliance is not convertible for use with other
gases, unless a certifi ed kit is used.
Installation Manual
Installation and Appliance Setup
Heatilator • ECLIPSE-32, ECLIPSE-36 Installation Manual • 2297-984 Rev. B • 6/15
WARNING:
FIRE OR EXPLOSION HAZARD
Failure to follow safety warnings exactly
could result in serious injury, death, or
property damage.
• DO NOT store or use gasoline or other fl am-
mable vapors and liquids in the vicinity of this
or any other appliance.
• What to do if you smell gas
- DO NOT try to light any appliance.
- DO NOT touch any electrical switch. DO
NOT use any phone in your building.
- Leave the building immediately.
- Immediately call your gas supplier from
a neighbor's phone. Follow the gas sup-
plier's instructions.
- If you cannot reach your gas supplier, call
the fi re department.
• Installation and service must be performed
by a qualifi ed installer, service agency, or the
gas supplier.
DANGER
DO NOT TOUCH GLASS
NEVER ALLOW CHILDREN
A barrier designed to reduce the risk of
burns from the hot viewing glass is provided
with this appliance and shall be installed for
the protection of children and other at-risk
individuals.
In the Commonwealth of Massachusetts installation must be
performed by a licensed plumber or gas fi tter.
See Table of Contents for location of additional Commonwealth
of Massachusetts requirements.
HOT GLASS WILL
CAUSE BURNS.
UNTIL COOLED.
TO TOUCH GLASS.
1

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the ECLIPSE-32 and is the answer not in the manual?

Questions and answers

Subscribe to Our Youtube Channel

Summary of Contents for Heatilator ECLIPSE-32

  • Page 1 See Table of Contents for location of additional Commonwealth gases, unless a certifi ed kit is used. of Massachusetts requirements. Heatilator • ECLIPSE-32, ECLIPSE-36 Installation Manual • 2297-984 Rev. B • 6/15...
  • Page 2: Table Of Contents

    B. Securing and Leveling the Appliance ....32  = Contains updated information. Heatilator • ECLIPSE-32, ECLIPSE-36 Installation Manual • 2297-984 Rev. B • 6/15...
  • Page 3: Installation Standard Work Checklist

    Comments: Further description of the issues, who is responsible (Installer/ Builder/ Other Trades, etc) and corrective action needed _____________________________________________________________________________________ _________________________________________________________________________________________________ _________________________________________________________________________________________________ Comments Communicated to party responsible ____________________ by ______________________on ___________ (Builder / Gen. Contractor/) (Installer) (Date) = Contains updated information. 2297-986 8/14 Heatilator • ECLIPSE-32, ECLIPSE-36 Installation Manual • 2297-984 Rev. B • 6/15...
  • Page 4: Product Specifi C And Important Safety Information

    (U.S. or Canada) BTU/h ECLIPSE-32 17,500 12,000 (0-2000 FT) (NG) ECLIPSE-32 17,000 13,500 1.25 mm (0-2000 FT) (LP) ECLIPSE-36 23,500 16,500 (0-2000 FT) (NG) ECLIPSE-36 20,500 16,500 (0-2000 FT) (LP) Heatilator • ECLIPSE-32, ECLIPSE-36 Installation Manual • 2297-984 Rev. B • 6/15...
  • Page 5: Requirements For The Commonwealth Of Massachusetts

    VENT DIRECTLY BELOW. KEEP CLEAR OF ALL OB- of the installation. STRUCTIONS”. See Gas Connection section for additional Common- wealth of Massachusetts requirements. Heatilator • ECLIPSE-32, ECLIPSE-36 Installation Manual • 2297-984 Rev. B • 6/15...
  • Page 6: Getting Started

    Non-corrosive leak check solution 1/2 - 3/4 in. length, #6 or #8 Self-drilling screws Caulking material (300ºF minimum continuous exposure rating) One 1/4 in. female connection (for optional fan). Heatilator • ECLIPSE-32, ECLIPSE-36 Installation Manual • 2297-984 Rev. B • 6/15...
  • Page 7: Framing And Clearances

    6-7/8 23-3/8 26-7/8 34-3/8 37-7/8 35-1/2 39-15/16 1014 8-13/16 8-13/16 16-5/16 16-5/16 25-3/4 30-3/4 12-7/8 15-3/8 15-7/8 15-7/8 6-5/8 6-5/8 2-3/16 2-3/16 30-1/16 33-9/16 Figure 3.1 Appliance Dimensions Heatilator • ECLIPSE-32, ECLIPSE-36 Installation Manual • 2297-984 Rev. B • 6/15...
  • Page 8 35-13/16 IN. Figure 3.2 Simon Decorative Front Dimensions CLEAN FACE DECORATIVE FRONTS CF-32 CF-36 27-1/4 IN. 23-3/4 IN. 35-13/16 IN. 30-13/16 IN. Figure 3.3 Clean Face Decorative Front Dimensions Heatilator • ECLIPSE-32, ECLIPSE-36 Installation Manual • 2297-984 Rev. B • 6/15...
  • Page 9: Clearances To Combustibles

    1581 1232 1746 5.D for Alcove 45-1/2 64-3/8 45-1/2 64-3/8 16-1/4 48-1/2 68-3/4 16-5/8 7-1/2 Installation ECLIPSE-36 1156 1067 1635 1156 1635 1232 1746 Figure 3.4 Appliance Locations Heatilator • ECLIPSE-32, ECLIPSE-36 Installation Manual • 2297-984 Rev. B • 6/15...
  • Page 10: Constructing The Appliance Chase

    ECLIPSE-36 1067 * Adjust framing dimensions for interior sheathing (such as sheetrock) C** Add 12 inches for rear venting with one 90º elbow. Figure 3.5 Clearances to Combustibles Heatilator • ECLIPSE-32, ECLIPSE-36 Installation Manual • 2297-984 Rev. B • 6/15...
  • Page 11: Termination Location And Vent Information

    Over 16/12 to 18/12 ..........7.0 Over 18/12 to 20/12 ..........7.5 Over 20/12 to 21/12 ..........8.0 * 3 foot minimum in snow regions Figure 4.1 Minimum Height From Roof To Lowest Discharge Opening Heatilator • ECLIPSE-32, ECLIPSE-36 Installation Manual • 2297-984 Rev. B • 6/15...
  • Page 12: Chimney Diagram

    2 sides beneath the fl oor. venting system does not meet these requirements. • Vinyl protection kits are suggested for use with vinyl siding. Figure 4.3 Minimum Clearances for Termination Heatilator • ECLIPSE-32, ECLIPSE-36 Installation Manual • 2297-984 Rev. B • 6/15...
  • Page 13: Approved Pipe

    WARNING! Risk of Fire or Asphyxiation. This appli- ance requires a separate vent. DO NOT vent to a pipe serving a separate solid fuel burning appliance. Heatilator • ECLIPSE-32, ECLIPSE-36 Installation Manual • 2297-984 Rev. B • 6/15...
  • Page 14: Use Of Elbows

    4-1/4 DVP12 8-1/2 DVP24 DVP36 25-1/2 DVP48 1219 DVP6A 3 to 6 76 to 152 2-1/8-4-1/4 54-108 DVP12A 3 to 12 76 to 305 2-1/8-8-1/2 54-216 Figure 4.4 Heatilator • ECLIPSE-32, ECLIPSE-36 Installation Manual • 2297-984 Rev. B • 6/15...
  • Page 15: Measuring Standards

    However, the vent attachment point and the fi restop loca- tion are considered to be supports. 1/4 in. max. TERMINATION (6 mm) 3 in. CLEARANCE  Figure 4.7 FLEX-VENT 1 in. CLEARANCE Figure 4.6 Heatilator • ECLIPSE-32, ECLIPSE-36 Installation Manual • 2297-984 Rev. B • 6/15...
  • Page 16 Note: There MUST be a 25% reduction in total H when using fl ex vent except when using the simple up and out installation (see Figure 4.6). Figure 4.8 Heatilator • ECLIPSE-32, ECLIPSE-36 Installation Manual • 2297-984 Rev. B • 6/15...
  • Page 17 fi rst elbow. • When using DVP-TB1 termination cap on top vented fi replaces, a three foot minimum vertical vent section is required before installing fi rst elbow. Figure 4.9 Heatilator • ECLIPSE-32, ECLIPSE-36 Installation Manual • 2297-984 Rev. B • 6/15...
  • Page 18 • When using SLP-HRC-SS and SLP-HRC-ZC- SS termination caps on top vented fi replaces, a one foot minimum vertical vent section is required before installing fi rst elbow. Figure 4.10 Heatilator • ECLIPSE-32, ECLIPSE-36 Installation Manual • 2297-984 Rev. B • 6/15...
  • Page 19 fl ame height. If the vent confi guration has a total vertical of 15-60 feet, an exhaust restrictor may be needed. The exhaust restrictor can be located in the Figure 4.12 appliance manual bag. Heatilator • ECLIPSE-32, ECLIPSE-36 Installation Manual • 2297-984 Rev. B • 6/15...
  • Page 20 Note: There MUST be a 25% reduction HORIZONTALLY in total H when using fl ex vent except when using the simple up and out installation (see Figure 4.6). Figure 4.14 Heatilator • ECLIPSE-32, ECLIPSE-36 Installation Manual • 2297-984 Rev. B • 6/15...
  • Page 21 Note: There MUST be a 25% reduction in total H when using fl ex vent except when using the simple up and out installation (see Figure 4.6). Figure 4.15 Heatilator • ECLIPSE-32, ECLIPSE-36 Installation Manual • 2297-984 Rev. B • 6/15...
  • Page 22 = 24 in. Max. (610 mm) components only. Figure 4.16 Rear Vent - Horizontal Termination = 9 in. (229 mm) Maximum One 45º Elbow Note: Use DVP Series components only. Figure 4.17 Heatilator • ECLIPSE-32, ECLIPSE-36 Installation Manual • 2297-984 Rev. B • 6/15...
  • Page 23 6 ft. 1.8 m 13-1/2 ft. 4.1 m HORIZONTALLY MAX. = 7-1/2 ft. (2.3 m) MAX. = 13-1/2 ft. (4.1 m) MAX. = 40 ft. (12.2 m) Figure 4.19 Heatilator • ECLIPSE-32, ECLIPSE-36 Installation Manual • 2297-984 Rev. B • 6/15...
  • Page 24 6-1/2 ft. 2.0 m 3 ft. 914 mm H MAX. = 6-1/2 ft. (2 m) V + H+ H MAX. = 40 ft. (12.2 m) INSTALLED HORIZONTALLY Figure 4.21 Heatilator • ECLIPSE-32, ECLIPSE-36 Installation Manual • 2297-984 Rev. B • 6/15...
  • Page 25 4.4 m MAX. = 7-1/2 ft. (2.3 m) MAX. = 14-1/2 ft. (4.4 m) MAX. = 40 ft. (12.2 m) Note: Use DVP Series components only. Figure 4.22 Heatilator • ECLIPSE-32, ECLIPSE-36 Installation Manual • 2297-984 Rev. B • 6/15...
  • Page 26: Coaxial To Colinear Venting

    CAUTION! DO NOT use any fl ue restrictor when vent- ing with the DV-46DVA-GCL adapter and LINK-DV30B kit. This could result in poor fl ame appearance, sooting, pilot malfunction, or overheating. Heatilator • ECLIPSE-32, ECLIPSE-36 Installation Manual • 2297-984 Rev. B • 6/15...
  • Page 27: Rear Vent

    10 ft. 3.05 m 0 ft. 0 mm Minimum 10 ft. 3.05 m Maximum 40 ft. 12.2 m 2 ft. 610 mm Maximum 40 ft. 12.2 m Figure 4.25 Heatilator • ECLIPSE-32, ECLIPSE-36 Installation Manual • 2297-984 Rev. B • 6/15...
  • Page 28: Vent Clearances And Framing

    * Shows center of vent framing hole for top or rear venting. The center of the hole is one (1) in. (25.4 mm) above the center of the horizontal vent pipe. Figure 5.2 Wall Penetration Heatilator • ECLIPSE-32, ECLIPSE-36 Installation Manual • 2297-984 Rev. B • 6/15...
  • Page 29: Ceiling Firestop/Floor Penetration Framing

    Figure 5.3 Installing Ceiling Firestop INSTALL ATTIC INSULATION SHIELDS BEFORE OR AFTER INSTALLATION OF VENT SYSTEM CEILING FIRESTOP CEILING FIRESTOP INSTALLED BELOW CEILING INSTALLED ABOVE CEILING Figure 5.4 Installing the Attic Shield Heatilator • ECLIPSE-32, ECLIPSE-36 Installation Manual • 2297-984 Rev. B • 6/15...
  • Page 30: Appliance Preparation

    The heat shield must remain in the vertical position. 2 SCREWS Figure 6.3 Replace the two screws as shown. Figure 6.6 Remove the insulation from the outer vent pipe. Heatilator • ECLIPSE-32, ECLIPSE-36 Installation Manual • 2297-984 Rev. B • 6/15...
  • Page 31 Use four self- tapping screws to secure gasket to outer wrap. Figure 6.9 Fold the center parts of the retaining band toward the center as shown. Remove the seal cap. Heatilator • ECLIPSE-32, ECLIPSE-36 Installation Manual • 2297-984 Rev. B • 6/15...
  • Page 32: Securing And Leveling The Appliance

    • Secure the appliance to the fl oor by inserting two screws through the pilot holes at the bottom of the appliance. NAILING TABS (BOTH SIDES) Figure 6.12 Proper Positioning and Securing of an Appliance Heatilator • ECLIPSE-32, ECLIPSE-36 Installation Manual • 2297-984 Rev. B • 6/15...
  • Page 33: Venting And Chimneys

    fl ue at the horizontal elbow joint to prevent the elbow from rotating. Use screws no longer than 1/2 in. (13 mm). If predrilling screw holes, DO NOT penetrate inner pipe. INCORRECT Figure 7.4 Seams Heatilator • ECLIPSE-32, ECLIPSE-36 Installation Manual • 2297-984 Rev. B • 6/15...
  • Page 34: Assemble Vent Sections (Slp Pipe)

    • Only outer pipes are sealed, sealing the inner fl ue is not required. • All unit collar, pipe, slip section, elbow and cap outer fl ues shall be sealed. Heatilator • ECLIPSE-32, ECLIPSE-36 Installation Manual • 2297-984 Rev. B • 6/15...
  • Page 35: Secure The Vent Sections

    Figure 7.10 Rotate Seams for Disassembly connection point to appliance. 120º Figure 7.11 Align and Disassemble Vent Sections Figure 7.8 Securing Vertical Pipe Sections 120º Figure 7.9 Securing Horizontal Pipe Sections Heatilator • ECLIPSE-32, ECLIPSE-36 Installation Manual • 2297-984 Rev. B • 6/15...
  • Page 36: Vertical Termination Requirements

    • Caulk the perimeter of the fl ashing where it contacts the roof surface. See Figure 7.13. • Caulk the overlap seam of any exposed pipe sections that are located above the roof line. Heatilator • ECLIPSE-32, ECLIPSE-36 Installation Manual • 2297-984 Rev. B • 6/15...
  • Page 37: Horizontal Termination Requirements

    • Rest the small leg on the extended heat shield on top of the pipe section to properly space it from the pipe section. Important Notice: Heat shields may not be fi eld constructed. Heatilator • ECLIPSE-32, ECLIPSE-36 Installation Manual • 2297-984 Rev. B • 6/15...
  • Page 38 DVP-TRAP1 can adjust 1-1/2 in. (3-1/8 to 4-5/8) DVP-TRAP2 can adjust 4 in. (5-3/8 to 9-3/8) DVP-HPC1 can adjust 2-1/8 in. (4-1/4 to 6-3/8) DVP-HPC2 can adjust 4-1/8 in. (6-3/8 to 10-1/2) Heatilator • ECLIPSE-32, ECLIPSE-36 Installation Manual • 2297-984 Rev. B • 6/15...
  • Page 39: Electrical Information

    3-volt transformer connected to permanent electrical service Copper ground attached GRN wire to GRN screw with inside box GRN wire Figure 8.1 Junction Box Detail Heatilator • ECLIPSE-32, ECLIPSE-36 Installation Manual • 2297-984 Rev. B • 6/15...
  • Page 40 PILOT IGNITOR MODULE 3 VAC TRANSFORMER ORANGE 3 VAC WHITE GROUND TO FIREPLACE PLUG IN CHASSIS BATTERY PACK WALL SWITCH Figure 8.2 Intellifi re Pilot Ignition (IPI) Wiring Diagram Heatilator • ECLIPSE-32, ECLIPSE-36 Installation Manual • 2297-984 Rev. B • 6/15...
  • Page 41 Figure 8.4 Fan Wiring with Rheostat RHEOSTAT JUNCTION BOX SWITCH TEMPERATURE Figure 8.3 Junction Box Wired to Wall Switch or BC10 SENSOR SWITCH BLUE Figure 8.5 Detail of Fan Wiring with Rheostat Heatilator • ECLIPSE-32, ECLIPSE-36 Installation Manual • 2297-984 Rev. B • 6/15...
  • Page 42: Gas Information

    4500 feet (1370 m). • If substituting for these components, please consult local codes for compliance. Check with your local gas utility to determine proper orifi ce size. Heatilator • ECLIPSE-32, ECLIPSE-36 Installation Manual • 2297-984 Rev. B • 6/15...
  • Page 43: Air Shutter Setting

    ECLIPSE-32 1/4 in. 1/2 in. ECLIPSE-36 1/4 in. 1/2 in. SHUTTER ADJUSTMENT Measure from left edge of slot to center of first stud. Figure 9.1 Air Shutter Adjustment Heatilator • ECLIPSE-32, ECLIPSE-36 Installation Manual • 2297-984 Rev. B • 6/15...
  • Page 44: Finishing

    0 IN. 0 IN. HIGH TEMPERATURE SEALANT (300° F/149° C MIN.) Figure 10.2 Clean Face Decorative Front Finishing Details TOP AND SIDE SEAL JOINT Figure 10.1 Noncombustible Facing Diagram Heatilator • ECLIPSE-32, ECLIPSE-36 Installation Manual • 2297-984 Rev. B • 6/15...
  • Page 45: Mantel And Wall Projections

    Dimension Diagram (Figure 3.1). Figure 10.6 Non-Combustible Zone Note: Clearance from opening to perpendicular wall. Figure 10.4 Non-Combustible Mantel Leg or Wall Projections (Acceptable on both sides of opening) Heatilator • ECLIPSE-32, ECLIPSE-36 Installation Manual • 2297-984 Rev. B • 6/15...
  • Page 46: Appliance Setup

    Clean/vacuum any sawdust that may have accumulated inside the fi rebox or underneath in the control cavity. LATCHES (BOTH BOTTOM AND TOP) GLASS ASSEMBLY Figure 11.1 Fixed Glass Assembly Heatilator • ECLIPSE-32, ECLIPSE-36 Installation Manual • 2297-984 Rev. B • 6/15...
  • Page 47: Install The Stones And Lava Rock

    4. Remove rock placement jig. Ensure that the stones are approximately 1/4 inch from the burner tube slot. Figure 11.3. Lava Rock Placed on Base Pan. Figure 11.5. Stones in Place. Heatilator • ECLIPSE-32, ECLIPSE-36 Installation Manual • 2297-984 Rev. B • 6/15...
  • Page 48: Install Fixed Glass Assembly

    Contact your dealer or Hearth & Home Technologies if the barrier is not present or help is needed to properly install one. For more information refer to the instructions supplied with your decorative door or front. Heatilator • ECLIPSE-32, ECLIPSE-36 Installation Manual • 2297-984 Rev. B • 6/15...
  • Page 49: Reference Materials

    14 in. (356 mm) 5 in. 12 in. (127 mm) (305 mm) 6 in. (152 mm) DVP-HVS (Vent Support) DVP-WS (Wall Shield Firestop) Figure 12.1 DVP vent components Heatilator • ECLIPSE-32, ECLIPSE-36 Installation Manual • 2297-984 Rev. B • 6/15...
  • Page 50 79 mm 117 mm Length DVP-TRAP 5-3/8 in. 9-3/8 in. Trap2 Horizontal Termination Cap 137 mm 238 mm DVP-TRAP2 DVP-TRAP1 DVP-TRAPK2 DVP-TRAPK1 DVP-HPC1 DVP-HPC2 Figure 12.2 DVP vent components Heatilator • ECLIPSE-32, ECLIPSE-36 Installation Manual • 2297-984 Rev. B • 6/15...
  • Page 51 13-7/8 in. 9-1/2 in. (352 mm) (241 mm) 26 in. 660 mm 14 in. (356 mm) DVP-HSM-B DRC-RADIUS Extended Heat Shield Cap Shield Figure 12.3 DVP vent components Heatilator • ECLIPSE-32, ECLIPSE-36 Installation Manual • 2297-984 Rev. B • 6/15...
  • Page 52 1 in. (25 mm) 7-3/4 to 10-3/8 in. 1-5/8 in. (197 to 264 mm) (41 mm) DVP-FBHT DVP-HPC FireBrickTermination Cap High Performance Cap Figure 12.4 DVP Vent Components Heatilator • ECLIPSE-32, ECLIPSE-36 Installation Manual • 2297-984 Rev. B • 6/15...
  • Page 53 10-1/2 in. (381 mm) 267 mm 10-7/8 in. 276 mm SLP-HRC-SS SLP-HRC-ZC-SS HORIZONTAL TERMINATION CAP DVP-TB1 DVP-TB1 SL-2DVP SLP90 ASSEMBLY DVP-TB1 HORIZONTAL TERMINATION CAP Figure 12.5 Vent Components Heatilator • ECLIPSE-32, ECLIPSE-36 Installation Manual • 2297-984 Rev. B • 6/15...
  • Page 54 100 FT PV Wire Harness PVI-WH100 separately. Use if the PVLP-SLP is installed in a high traffi c area. PVLP-HS PVLP-BEK Heat Shield Brick Kit  Figure 12.6 PVLP-SLP Vent Components Heatilator • ECLIPSE-32, ECLIPSE-36 Installation Manual • 2297-984 Rev. B • 6/15...
  • Page 55 8-11/16 in. 1-1/2 in. 12 in. 5-1/2 in. 220 mm 38 mm 146 mm 305 mm SLP-WS SLP-FS Wall Shield Firestop Ceiling Firestop Figure 12.7 SLP Series Vent Components Heatilator • ECLIPSE-32, ECLIPSE-36 Installation Manual • 2297-984 Rev. B • 6/15...
  • Page 56 14-7/16 in. 367 mm 26 in. 660 mm 2-5/16 in. 14-7/16 in. 59 mm 367 mm DVP-HSM-B SLP-WT-BK Extended Heat Shield Wall Thimble-Black Figure 12.8 SLP Series Vent Components Heatilator • ECLIPSE-32, ECLIPSE-36 Installation Manual • 2297-984 Rev. B • 6/15...
  • Page 57 1 in. (25 mm) 13-1/2 in. 343 mm 7-3/4 to 10-3/8 in. (197 to 264 mm) DVP-FBHT SLK-SNKD Snorkel Horizontal Termination Cap Termination Cap Figure 12.9 SLP Series Vent Components Heatilator • ECLIPSE-32, ECLIPSE-36 Installation Manual • 2297-984 Rev. B • 6/15...
  • Page 58 COAXIAL to COLINEAR VENTING LINK-DV30B 768-380A DV-46DVA-GCL Flex Liner Kit Stainless Steel Flex Pipe Coaxial/Colinear Appliance Connector DVP-2SL Adapter Figure 12.10 Coaxial to Colinear Vent Components Heatilator • ECLIPSE-32, ECLIPSE-36 Installation Manual • 2297-984 Rev. B • 6/15...
  • Page 59: Accessories

    Please contact your Heatilator dealer with any questions or concerns. For the location of your nearest Heatilator dealer, please visit www.heatilator.com. Printed in U.S.A. - Copyright 2015 Heatilator • ECLIPSE-32, ECLIPSE-36 Installation Manual • 2297-984 Rev. B • 6/15...

This manual is also suitable for:

Eclipse-64Eclipse-36