10 Decommissioning
10.1 Disassembly
1. Open the Sunny Boy as described in section 7.1 "Opening the Sunny Boy" (page 29).
2. Remove all cables from the Sunny Boy.
3. Close the Sunny Boy: fasten the housing cover to the Sunny Boy with the 4 screws.
4. Loosen the cylinder head screw between the Sunny Boy and wall mounting bracket.
5. Dismantle the Sunny Boy by lifting it out of the wall mounting bracket.
10.2 Packaging
If possible, always package the Sunny Boy in the original packaging. If this is no longer available,
you can also use an equivalent box that fulfills the following requirements:
• Suitable for loads up to 28 kg
• With handle system
• Completely closable
10.3 Storage
Store the Sunny Boy in a dry place where ambient temperatures are always between -25 °C
and +60 °C.
10.4 Disposal
Dispose of the Sunny Boy at the end of its service life in accordance with the disposal regulations for
electronic waste which apply at the installation site at that time. Alternatively, send it back to SMA
Solar Technology with shipping paid by sender, and labeled "ZUR ENTSORGUNG" ("for disposal").