Chapter 3: Installing an E4G Series Router

Installing the E4G-200 Series Cell Site Routers

The installation instructions for the E4G-200 and E4G-200-12x routers is the same. When you unpack the
E4G-200 series cell site router (either E4G-200 or E4G-200-12x), verify that the package contains the
following items:
E4G-200 or E4G-200-12x router
2 rack-mounting brackets with 8 screws
Ethernet console cable
DB-9-to-RJ-45 adapter
2 pluggable DC terminal block connectors (Dinkle part number 2ESDVM-03P)
You need the following additional materials to ground the router and connect it to power:
#14 AWG stranded copper cable for grounding the router and for connecting the router to the
DC power source
Recommended insulation colors are:
-
Green or green with yellow stripe for the ground connection
-
Red and black for the power and return connections
Connection hardware appropriate to the installation site:
-
Hardware for connecting the ground wire to the site grounding point
-
Hardware for connecting the power wires to the DC source
Stripping tool
Torque screwdriver and wrench or torque driver with attachments for tightening screws
-
The ground lug requires a 1/4-inch screwdriver tip.
-
The screws on the DC power connector require a 1/8-inch straight screwdriver tip.
Installing the E4G-200 series router includes the following tasks:
1 Install the router in a rack.
2 Ground the router.
3 Connect the router to power.
4 Install the clock module (optional) or T1/E1 module (optional).
5 Connect the alarms cable (optional).
6 Connect the console cable and perform initial configuration.
48
E4G Series Routers Hardware Installation Guide