3 INSPECTION AND MAINTENANCE

fig. 50
Annual inspection
112952.LT.GB.W7H.053
127768-271011
The Remeha Avanta Plus is practically maintenance free but
should be inspected annually.
If during the annual inspection the flue gas analysis indicates
that the values are outside the figures given in table 11, main-
tenance work should be carried out as described in par.3.2.
Also carry out maintenance if the ionisation read-out value is
lower than 3 or higher than 9µA.
Only Remeha spare parts/materials should be used.
All service and maintenance must be carried out by a qualified
Engineer with the relevant training and certification (i.e. ACS -
IEE registrations etc).
3.1
The annual inspection of the Remeha Avanta Plus can be lim-
ited to the following checks:
- Check the water pressure, see par. 3.1.1;
- Check the flue pipes and air supply pipes for leaks, see par.
3.1.2;
- C heck and clean (if necessary) the condensate siphon, see
par. 3.1.3;
- C heck the ignition electrode (change if necessary), see par.
3.1.4;
- Check the combustion and flame pattern, see par. 3.1.5;
- Fill in the Benchmark Service Record on the inside back
pages of this document.