Aarrow BK047 User Manual

Aarrow BK047 User Manual

Conventional flue gas stove

Advertisement

Quick Links

Installation / Servicing Instructions
& User Manual
Sherborne GSL
Conventional Flue Gas Stove
PLEASE RETAIN THESE INSTRUCTIONS FOR FUTURE REFERENCE
THIS STOVE IS NOT SUITABLE FOR TIMBER FRAMED PROPERTIES
BK047
FOR USE IN COUNTRIES
GB & IE
Gas council ID Number
NG - 32-248-06
LPG - 32-248-07
EN 613:2003
Rev 08
August 2009
Part No. AFGS1095

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the BK047 and is the answer not in the manual?

Questions and answers

Subscribe to Our Youtube Channel

Summary of Contents for Aarrow BK047

  • Page 1 & User Manual Sherborne GSL Conventional Flue Gas Stove PLEASE RETAIN THESE INSTRUCTIONS FOR FUTURE REFERENCE THIS STOVE IS NOT SUITABLE FOR TIMBER FRAMED PROPERTIES BK047 FOR USE IN COUNTRIES GB & IE Gas council ID Number NG - 32-248-06...
  • Page 2: Table Of Contents

    SPARE PARTS 45-47 Fitting and arranging Logs (LPG) 21-22 Installation Of The Remote Control 23-26 GUARANTEE System FINAL FACTORY CHECK LIST Commissioning Of The stove Fire Testing Advise The End User Building Control Check List Page 2 Aarrow Sherborne GSL CF...
  • Page 3: Safety Notices

    „Hazardous waste‟ and may Asbestos, hazardous or any banned materials be disposed of at a tipping site licensed for have not and will not be included in this product. the disposal of industrial waste. Aarrow Sherborne GSL CF Page 3...
  • Page 4: Installation Instructions

    (see fig 2a). Please observe the data, safety and warning labels attached to this plate. DO NOT remove this plate from the stove. Page 4 Aarrow Sherborne GSL CF...
  • Page 5: Contents List & Part Identification

    • GAS SERVICE TAP • GLASS SCREWS Canopy Cover Plate PART IDENTIFICATION Canopy Infill piece Outer Body & Canopy Stove Engine Assembly Glass Frame Assembly Fire Doors Valve Cover Dummy Fuel Retainer Fig. 2b. Aarrow Sherborne GSL CF Page 5...
  • Page 6: Important Notices

    Servicing instruction & part taken as overriding statutory requirements identification numbers are given towards the back of the manual.  Only use genuine Aarrow parts for CERTIFICATION replacements.  Ventilation, no purpose built ventilation This appliance is CE certified for performance is normally required, normal adventi- and safety.
  • Page 7: Technical Data

    GB,GR,IE,IT, GR,IE,IT,PT supply point may be inaccessible, therefore NO,PT,SE it may be necessary to route the pipe for the gas supply before installing the stove into Gas Council 32-248-06 32-248-07 its recess. Id Number Aarrow Sherborne GSL CF Page 7...
  • Page 8: Preparation Of The Stove

    (including curtains) within 1 metre of the Combustible Wall. stove. B= 200mm Minimum Per Side to a For details of combustibles and non- Combustible Wall. combustible shelf clearances see graphs 1 & 2 on page 9. Fig. 4b Page 8 Aarrow Sherborne GSL CF...
  • Page 9: Shelf Clearances

    2. Shelf Requirement Graph 2 Shelf Depth (mm) Warning : No shelf is to be used with a top flued appliance, where it has to pass through a shelf. Aarrow Sherborne GSL CF Page 9...
  • Page 10: Flue System

    BS4543:Part2 (often called “Class 1 prefabricated metal chimney”) To ensure the flue gases are kept warm an insulated chimney system should be used if the chimney is positioned outside the building. Page 10 Aarrow Sherborne GSL CF...
  • Page 11: Fitting Flue Spigot And Blanking Plate

    CLOSURE PLATES If a closure plate is used for sealing off the chimney or fireplace it can be made of metal (e.g. aluminium sheet) or fireplace board (see fig 6 a/b/c on page 12) however Aarrow Sherborne GSL CF Page 11...
  • Page 12 INSTALLATION INSTRUCTIONS Fig. 6c Y=See Graph 1 Fig. 6a Fig. 6b Page 12 Aarrow Sherborne GSL CF...
  • Page 13: Connecting The Gas Supply

    Step 6. Disconnect manometer and re-tighten the outlet pressure tap screw. Do not over tighten To check the pressure to the burner. This must be carried out with all other gas Step 7. Replace the valve control cover Aarrow Sherborne GSL CF Page 13...
  • Page 14: Fitting And Arranging Coals

    12 to 13j. , otherwise soot deposits or incomplete combustion will take place. Warning : An incorrect coal layout may cause soot to build up on the inside of the stove and therefore invalidate the guarantee. PART IDENTIFICATION Fig. 9. Random Loose Coals Page 14 Aarrow Sherborne GSL CF...
  • Page 15 Rear Lip Of Pilot Cut Notch In Burner Out Notch Coal Matrix Fig. 11. Fig. 10. General Loose Coal Positions Fig. 12. Aarrow Sherborne GSL CF Page 15...
  • Page 16 FIG 13d. FIG 13b. Coal Position Notch FIG 13c. Note : Do not obstruct or cover the circular gas ports with the loose coals. FIG 13d. Page 16 Aarrow Sherborne GSL CF...
  • Page 17 FIG 13g. Coal 8, should be positioned, so that it rests diagonally, upon all four base matrices and is therefore central to the fire box opening. Note : Coal 8, central, across all base matrices. FIG 13g. Aarrow Sherborne GSL CF Page 17...
  • Page 18 8) The coal layout is now complete, and should look like Fig.13j. NOTE, take care, not to disturb any of the loose coal positions during the fitment of the glass panel, otherwise this will have to be removed and the coals re-positioned again. Page 18 Aarrow Sherborne GSL CF...
  • Page 19: Fitting And Arranging Logs (Ng)

    The logs and matrix are fragile, ensure they are handled carefully. Ensure location is correct. Do not force the matrix into position. If the logs and or the rear matrix are damaged, then they must be replaced with a genuine Aarrow parts. Ensure the appliance is cold before placement.
  • Page 20 Sitting otherwise this will have to be removed and the the upper portion of the central log onto the logs re-positioned again. edge of the upper corner of the curved left hand log. Page 20 Aarrow Sherborne GSL CF...
  • Page 21 Ensure location is correct. Do not force the matrix into position. If the logs and or the rear matrix are damaged, then they must be replaced with a genuine Aarrow parts. Ensure the appliance is cold before placement. Warning : An incorrect log layout may cause soot to build up on the inside of the stove and therefore invalidate the guarantee.
  • Page 22 The LPG log lay out is now complete. Fig. 22. NOTE, take care, not to disturb any of the logs positions during the fitment of the glass panel, otherwise this will have to be removed and the logs re-positioned again. Page 22 Aarrow Sherborne GSL CF...
  • Page 23: Installation Of The Remote Control

    Micro-switch Fig. 23. Technical Data Ambient temperature range Remote and receiver Max. 140°F / 60°C Max. 356°F / 180°C Connecting cable Batteries Quality Alkaline Handset: 1 x 9v block Receiver: 4 x 1.5v AA Aarrow Sherborne GSL CF Page 23...
  • Page 24 5, Take the micro switch and fix to the front of the valve cover with the self tapping screw provided. The switch is located onto the lug moulded within the valve cover, next to knob B, (see fig. 24e) Wiring Knob B. Connections Micro Switch Fig. 24e Page 24 Aarrow Sherborne GSL CF...
  • Page 25 ASSEMBLE RECEIVER Important The remote system is intended for use with original Aarrow parts only. 1, Carefully push the multi block connector on to the connection within the receiver unit as shown in Fig. 25a. This connector can only fit one way, so ensure the slot in the receivers board lines up with the moulding within the multi block connection.
  • Page 26 2, The remote is now ready to use. In the event of battery failure the flame height can still be adjusted manually using the valve (Knob B). NOTE: Please note, the placement of the remote control (temperature sensor) is important to assure proper temperature regulation. Please refer to the user instructions. Page 26 Aarrow Sherborne GSL CF...
  • Page 27: Commissioning Of The Stove

    Step 5. If there is an extractor fan in any room, this must be turned on and any doors between it and the fire left open, repeat the spillage test Fig. 28 Aarrow Sherborne GSL CF Page 27...
  • Page 28: Advise The End User

    (including curtains) must not be placed within one metre of the stove. Leave the instruction manual with the end user. Page 28 Aarrow Sherborne GSL CF...
  • Page 29: Building Control Check List

    I/We the undersigned confirm that the above details are correct. In my opinion, these works comply with the relevant requirements in part J of Schedule 1 of the Building regulations. Print name and title…………………………………………………………………..Profession………………………………….. Capacity……………………………………………………………………………...Telephone No. …………………………….. Address………………………………………………………………………………………………..Postcode………………….. Signed………………………………………………………………………………..Date………………………………………... Registered member of. (e.g. GAS SAFE REGISTER, OFTEC, HETAS, NACE, NACS)……………………………………….. Aarrow Sherborne GSL CF Page 29...
  • Page 30: Servicing

    Step 3. Disengage locking levers, 1 per side  Remove the remaining top screw, the frame and glass will now be loose and can be removed.  The frame is slotted at the base for ease of removal. Aarrow Sherborne GSL CF Page 30...
  • Page 31: Burner & Valve Assembly Removal

    Step 6. Remove the base coal matrix (four pieces) take care not to damage the matrix, See page 14. Step 7. Remove the 2 no. self tapping screws each side of the injector as shown in Fig. 30. Aarrow Sherborne GSL CF Page 31...
  • Page 32: Annual Service

    Step 19. If the stove is top flued, proceed to fit components are damaged, they must be the top flue infill piece (see page 30, step 1b). replaced with original Aarrow parts. Place the valve cover in front of the control valve.
  • Page 33: Fault Diagnosis

    Check If Gas Pilot OSD Is Passing Assembly From Control Valve ? Replace Control Valve NOTE : OSD Pilot Investigate Control (Oxygen Sensing Device) Valve Operation & Replace If Necessary Replace Pilot OSD Assembly Aarrow Sherborne GSL CF Page 33...
  • Page 34: Annual Service Record

    Company Work Carried Out Signature Should you have any questions about your Aarrow Sherborne GSL gas stove that are not covered in this manual please contact your Aarrow stove retailer. Please keep all repair receipts safely. Please ensure you have this manual available when an engineer visits so they can complete the service...
  • Page 35: User Instructions

    USER INSTRUCTIONS Aarrow Sherborne GSL CF Page 35...
  • Page 36: To Ignite The Pilot

    „A‟ is set in the off position. (See Fig.31e). Fig. 31c NOTE: This lighting procedure does not have to be carried out every time the stove is used, provided the pilot is left alight. Page 36 Aarrow Sherborne GSL CF...
  • Page 37: To Ignite The Burner

    It is best cleaned using a soft brush. Do not Do not try to force the control, wait the 60 allow moisture to remain on the stove while cold seconds. or surface rust may occur. Aarrow Sherborne GSL CF Page 37...
  • Page 38: Operation Of Remote Control

    (eg: vacation) so that it cannot receive commands from the remote transmitter. Exercise caution when leaving the appliance unattended, and in exceptional cases, sound waves from sources other than the transmitter can cause changes in the flame height adjustment. Page 38 Aarrow Sherborne GSL CF...
  • Page 39 Press TIMER again to set the second heating period, P2* (Start) and P2) (Finish).  Store both heating periods by pressing TIMER again. NOTE: If only one heating period is desired, programme the same time for P2* and P2) as for P1* and P1). Aarrow Sherborne GSL CF Page 39...
  • Page 40 4no. (1.5V AA) batteries and replace the cover. Please ensure correct polarity with the battery terminals. See Fig. 34. NOTE: If the batteries lose power, the flame height can be adjusted by manually turning knob „B‟, see page 36. Page 40 Aarrow Sherborne GSL CF...
  • Page 41 (eg: vacations) so that it cannot receive commands from the remote control. Exercise caution when leaving the appliance unattended, in exceptional cases, sound waves from other sources, other than the remote transmitter can cause changes in flame height adjustment. Aarrow Sherborne GSL CF Page 41...
  • Page 42: Important Notices

    The current Gas Safety (Installation and Use) towards the back of the manual. Regulations (as amended).  Only use genuine Aarrow parts for The Building Regulations for England and Wales Replacement. 2000 ref Approved Document J 2002 edition (issued by the DTLR).
  • Page 43: Shelf Clearances

    2. Shelf Requirement Graph 2 Shelf Depth (mm) WARNING : No shelf is to be used with a top flue appliance, where it has to pass through a shelf. Aarrow Sherborne GSL CF Page 43...
  • Page 44: Options & Accessories

    Add On Canopy A traditional raised add on canopy is available for your Sherborne GSL stove, to AOCSHB complete the authentic look. The canopy can be fitted after the stove has been installed. Page 44 Aarrow Sherborne GSL CF...
  • Page 45: Spare Parts

    (BRAY 82/400) 5. Injector LPG AFGS1124 (BRAY 82/160) 6. Pilot Assembly AFGS1130 (NG: SIT 9043) 7. Pilot Assembly AFGS1131 (LPG: SIT 9228) 8. Top Burner AFGS1126 Assembly NG 9. Top Burner AFGS1127 Assembly LPG Aarrow Sherborne GSL CF Page 45...
  • Page 46 11. Fire Door Set (Complete With AFGS1128 Handles) 12. Glass Frame AFGS1093 Assembly 13. Hinge Kit With AFS047 Fixings 14. Dummy Fuel AFGS1118 Retainer 15. Instruction AFGS1095 Manual 16. Stove Glass AFGS1096 Rope Gasket (Body) Self Adhesive Page 46 Aarrow Sherborne GSL CF...
  • Page 47 AFGS1098 Plate 18. Top Flue Infill AFGS1120 Piece 19. Valve Cover AFGS1119 20. Flue Spigot AFGS1129 Complete With Rope Gasket 21. Hot Plate AFGS010 Complete With Rope Gasket 22. Hot Glove AFS1285 (Heat Resistant) Aarrow Sherborne GSL CF Page 47...
  • Page 48: Guarantee

    This does not apply to items which would be subject to fair wear or tear. However, should you have any problems with your appliance, please contact your Aarrow stove stockist who will have the knowledge and facilities to help you.
  • Page 49 NOTES Aarrow Sherborne GSL CF Page 49...
  • Page 50: Final Factory Check List

    FINAL FACTORY ASSEMBLY CHECK LIST Model ……………………………... Serial No …………………………... ALL TYPES I’ve checked it QUALITY and it’s OK! FINISH INSTRUCTION MANUAL GAS SERVICE TAP & 8no. GLASS FIXING SCREWS ASSEMBLED BY ……………… FLUE SPIGOT OUTLET HOT PLATE CHECKED BY …………………. OUTER SLAB CANOPY COVER OUTER SLAB CANOPY INFILL OUTER BODY ASSEMBLY...