Vv To 600 I\Vv Stationary Emergency Diesel Engine Driven Generator Sets; Service Maintenance Interval Information - Generac Power Systems 13694330200 Owner's Manual

Stationary emergency generator
Table of Contents

Advertisement

Maintenance
500 KW TO 600 KW STATIONARY EMERGENCY DIESEL ENGINE DRIVEN
GENERATOR SETS
Following Is a recommended maintenance schedule for stationary emergency diesel engine driven generator sets from 500 kW to 600 kW in
size. The established intervals in the schedule are the maximum required when the unit is used in an average service application. They will need
to be decreased (performed more frequently) if the unit is used in a severe application. Use the unit hour meter or calendar time, whichever
occurs first, from the previous maintenance interval to determine the next required maintenance interval.
NOTE: Add 20% to all times noted for 12 cylinder or larger engines.
14
WARNINGll
A
To prevent injury, disable the generator set from starting and/or connecting to the load by setting the
~ control panel Auto-Oft-Manual switch to the "Off' position, removing the control panel fuse, turning
oft the battery charger, and removing the negative battery cable before performing any maintenance.
NOTE: The battery charger must be turned oft BEFORE removing the battery cable to prevent an over
current condition from burning out sensitive control panel components and circuits. Following all
maintenance, reverse these steps to insure the unit Is returned to standby setup for normal operation
when required.
SERVICE MAINTENANCE INTERVAL INFORMATION
The various service maintenance intervals are designated by interval numbers as follows:
1.
An early inspection of the generator set to insure it is ready to operate when required and to identify any potential problem areas. Performed
monthly or following each 10 hours of operation of the unit and requires approximately .5 man-hours per unit to complete.
1A. A break-in service inspection of the generator set to insure it is ready to operate, transfer to, and carry the load when required, and to
identify any potential problem areas. Performed ONLY ONCE following the first six months or the first 50 hours of operation after purchase
of the unit and requires approximately 2.5 man-hours per unit to complete.
2.
An operational inspection of the generator set to insure it is ready to operate and carry the load when required, and to identify any potential
problem areas. Performed semi-annually or following each 50 hours of operation of the unit and requires approximately 1.5 man-hours
per unit to complete.
3.
A mid-level inspection of the generator set to insure it is
to operate and carry the load when required, and to identify any potential
problem areas. Performed annually or
each 100 hours of operation of the unit and requires approximately 4.
a
man-hours per
unit to complete.
4.
A comprehensive inspection of the generator set to insure it is properly serviced and ready to operate and carry the load when required,
and to identify any potential problem areas. Performed biannually or following each 250 hours of operation of the unit and requires
approximately 8.0 man-hours per unit to complete.
20