2.0 Installation Regulations and Requirements

The installation of ProCon HT boilers must be in accordance with the relevant
requirements of Gas Safety (Installation & Use) Regulations 1994, Health & Safety at
Work Act, Building Regulations, IEE Regulations, Construction (Design & Management)
Regulations 1994, Local Authority Bye-Laws, National, Fire Regulations and Insurance
Company requirements.
The following Codes of Practice are also applicable:-
BS 5449: 1990 Specification for forced circulation hot water central heating systems for
domestic premises.
BS 6644: 2005 Specification for gas fired hot water boilers of rated inputs between
70kW (net) and 1.8MW(net) (2nd and 3rd family gases).
BS 6798: 1987 Specification for installation of gas fired hot water boilers of rated input
not exceeding 60 kW.
BS 6880: 1988 Code of Practice for low temperature hot water heating systems of
output greater than 45kW. Parts 1, 2 & 3.
BS 6891: 1988 Specification for installation of low pressure gas pipework of up to 28mm
(R1) in domestic premises (2nd family gases)
BS 7593: 1992 Code of Practice for treatment of water in domestic hot water central
heating systems.
BS 7671: 1992 Requirements for electrical installations. IEE Wiring Regulations. Sixteenth
edition.
CISBE Guide reference sections B7, B11 and B13.
CP342 Part 2: 1974 Code of Practice for centralized hot water supply.
GE/UP/2
Gas installation pipework, boosters and compressors on industrial and
commercial premises.
IGE/UP/4 Commissioning of gas fired plant on industrial and commercial premises
IGE/UP/10 Installation of gas appliances in industrial and commercial premises. Part 1:
Flued appliances.
And any addition prevailing regulation and or code of practice not detailed above.

2.1 Appliance Warranties

All MHG appliances enjoy a full 24 month warranty as detailed in our terms and
conditions.
"The guarantee period shall begin on the day of commissioning, or at latest 3 months
after delivery has been made.
The customer shall only be able to claim against MHG under guarantee if the
commissioning of the object of delivery has been carried out by MHG staff or the
authorised supplier, if the customer has followed MHG's instructions relating to the
treatment and maintenance of the object of delivery, and if no replacement parts of
outside origin have been fitted.
Parts subject to wear such as ignition electrodes, seals etc. are strictly excluded from the
guarantee."
In addition to the above warranties, the Primary Heat Exchangers carry a 60 month
guarantee against manufacturing or material defect.
MHG Heating Ltd, Unit 4 Epsom Downs Metro Centre, Waterfield, Tadworth, Surrey, KT20 5LR
P:0845 6448802 F:0845 6448803 E:
info@mhgheating.co.uk
W: www.mhgheating.co.uk
7
011011

Hide quick links:

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the ProCon HT and is the answer not in the manual?

Subscribe to Our Youtube Channel

This manual is also suitable for:

Htp 150Htp 225Procon ht 150Procon ht 225

Table of Contents