Tools and materials

The following tools are required for installation:
Phillips screwdriver
10-mm hex-nut driver
The following items are supplied with the rack:
Screws
Hex nuts
Cage nuts
Cage nut-fitting tool

Selecting a site

WARNING: To prevent fire or electric shock, install the unit in a temperature- and
humidity-controlled indoor environment, free of conductive contaminants.
When selecting a site, consider the following factors:
Elevated operating ambient temperature—If the equipment is installed in a closed or multi-unit rack
assembly, the operating ambient temperature of the rack environment might be greater than room
ambient temperature. Install the equipment in an environment compatible with the operating
temperature
Reduced air flow—In the rack, the rate of air flow required for safe operation of the equipment must
not be compromised.
Circuit overloading—Consideration should be given to the connection of the equipment to the supply
circuit and the effect that overloading of the circuits might have on overcurrent protection and supply
wiring. Appropriate consideration of equipment nameplate ratings should be used when addressing
this concern.
Reliable earthing—Reliable earthing of rack-mounted equipment should be maintained. Particular
attention should be given to supply connections other than direct connections to the branch circuit,
such as the use of power strips.
Electrical requirements—All models require a dedicated (unshared) branch circuit, suitably rated for
the specific UPS as stated in "Input specifications

Readying the equipment

Check the battery recharge date specified on the label that is affixed to the shipping carton.
1.
IMPORTANT: Do not use the battery if the recharge date has passed. If the date on the battery recharge
date label has passed without the battery being recharged, contact an HP authorized service representative
for directions.
Transport the packaged unit to its installation location.
2.
Unpack the equipment near the rack where the unit will be assembled.
3.
CAUTION: Always plan the rack installation so that the heaviest item is on the bottom of the rack. Install
the heaviest item first, and continue to populate the rack from the bottom to the top.
("Environmental
specifications" on page 46).
("UPS input
specifications" on page 43)" .
Installation 12

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents