Magnet Mounting - Cisco Catalyst 2960 Hardware Installation Manual

Hide thumbs Also See for Catalyst 2960:
Table of Contents

Advertisement

Installing the Switch
3.
For configuration instructions about using the CLI setup program, go to
Switch with the CLI-Based Setup Program."

Magnet Mounting

This section is specific to the Catalyst 2960 8-port switches. For information applicable to the other
Catalyst 2960 switches, see
To mount a switch by using the magnet, follow these steps:
Place one side of the magnet against the bottom of the switch, as shown in
Step 1
Figure 3-7
2
1
2
Step 2
Mount the magnet and switch on a metal surface.
After the switch is attached to the mounting magnet, do these tasks to complete the installation:
1.
2.
3.
Catalyst 2960 Switch Hardware Installation Guide
3-14
Connect to the front-panel ports. See the
on page
2-18, the
"Connecting to SFP Modules" section on page
Dual-Purpose Port" section on page 2-22
Chapter 2, "Switch Installation (24- and 48-Port Switches)."
Mounting the Switch with a Magnet
1
3
Metal surface
3
Switch
Magnet
Power on the switch. See the
Connect to a 10/100 or 10/100/1000 port, and run Express Setup. See the switch getting started guide
for instructions.
Connect to the front-panel ports. See the
on page
2-18, the
"Connecting to SFP Modules" section on page
Dual-Purpose Port" section on page 2-22
"Connecting to the 10/100 and 10/100/1000 Ports" section
to complete the installation.
"Verifying Switch Operation" section on page
"Connecting to the 10/100 and 10/100/1000 Ports" section
to complete the installation.
Chapter 3
Switch Installation (8-Port Switches)
2-19, and the
"Connecting to a
Appendix C, "Configuring the
Figure
3-7.
3-6.
2-19, and the
"Connecting to a