Placing the boiler

6
Placing the boiler
This chapter explains how to place the boiler and
position it in the boiler room.
SYSTEM DAMAGE
through frost.
Place the boiler in a frost-free room.
CAUTION!
The boiler is very heavy when full. Check that the floor
can bear the weight before installation.
6.1

Clearances

A space of at least 33 inches is recommended in front of
the boiler with the door open to allow sufficient access
space for operation and maintenance. When the door is
closed, a minimum clearance of 2 inches is required at
the front and sides, 6 inches clearance is also required
for the flue pipe and 30 inches clearance to the ceiling
(
Fig. 5). The installation location and the base must
be smooth and horizontal. The boiler may be installed on
a flammable base, but not on carpet.
6.2

Leveling the boiler

Level the boiler block vertically and horizontally. Use
metal wedges or metal strips if necessary.
We reserve the right to make any changes due to technical modifications.
Installation and maintenance instructions Logano G334 X gas-fired boiler • Issue 09/2005
Fig. 5
Required clearances in the boiler room
6