4.4 Baffle Installation and Brick Notes
1.
Stack the baffle boards (A) on top of the vermiculite boards (B) as shown in figure 3.4a .
2.
Put them on the horizontal air duct (C) (see figure 3.4b). Afterwards, push them towards the bottom
and sides so that they rest on the back of the firebox (D) and on the side air ducts. Install the baffle
support/extension (H) ensuring that it fits between the front risers and hold it in place. Install the front
secondary air tube as show in figure 3.4c ensuring air holes face forward. Install the cotter pins as in fig 4.3.
Installing the front secondary air tube (E) will stabilize baffle assembly during the next step.
Figure 3.4a
Figure 3.4b
/21