Installing the HP 5400 zl Switches
Installation Procedures
Figure 2-4. Back of switch with power supply fully installed

4. Verify the Switch Passes Self Test

After you have installed any modules and the optional second power supply,
but before mounting the switch in its network location, you should first verify
it is working properly by plugging it into a power source and verifying it passes
its self test.
If you have installed a second power supply, repeat these procedures with the
second power supply to verify it works correctly also.
1.
Figure 2-5. Power connector on back of switch
2-12
Connect the power cord supplied with the switch to the power connector
on the back of the switch, and then into a properly grounded electrical
outlet.
tighten the four screws
Connect power cord to
power connector