4.3.3. PREPARING FOR EXTENDED STORAGE

To prepare the OTS for extended storage, perform the following:
1. Check the monocular for serviceability as outlined in item
4.1 of this manual.
2. Remove the batteries.
3. Clean the monocular and accessories.
4. Replace all items in the case.
4.3.4. HEADMOUNT MAINTENANCE
A. REMOVAL AND INSTALLATION OF BROWPAD
1. Remove old browpad (Figure 4-1) by grasping the headband.
2. Replace the browpad by gently pressing on the new brow-
pad and smoothing out any wrinkles in new browpad.
Figure 4-1. Removal and Installation of Browpad
B. REMOVAL AND INSTALLATION OF CHINSTRAP
1. Remove the chinstrap (Figure 4-2) by unsnapping the Wel-
cro tape from the left side of the headband. Unbuckle the
chinstraps from narrow strap assembly.
2. Replace the chinstrap by using the Welcro tape on the left
side of the headband. Lace the right straps into their re-
spective sliding bar buckles on the right side of the head-
band for correct lacing (Figure 4-2).