Figure 4-2 Power-Strip Power Cord Routing - NEC Express5800/A1160 Installation Manual

Hw
Hide thumbs Also See for Express5800/A1160:
Table of Contents

Advertisement

1.
Route the power-strip power cords down the cable manager and exit the bottom of
the cabinet. After all power cables are routed, secure the cables to the cabinet
frame using cable ties.
Do not connect the power strips to the premises wiring at this time.

Figure 4-2 Power-Strip Power Cord Routing

2.
Connect the cell power cables between the cell and the appropriate power strips.
Route the cables in the cable manager and secure them.
Power Cabling for 200V to 240V Systems
4-3