NEC Express5800 120Ed Installation Procedures Manual
NEC Express5800 120Ed Installation Procedures Manual

NEC Express5800 120Ed Installation Procedures Manual

Rack mount kit
Hide thumbs Also See for Express5800 120Ed:

Advertisement

Quick Links

Express5800/120Ed

Rack Mount Kit

Installation Procedures

PN: 455-01607-001

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the Express5800 120Ed and is the answer not in the manual?

Questions and answers

Summary of Contents for NEC Express5800 120Ed

  • Page 1: Rack Mount Kit

    Express5800/120Ed Rack Mount Kit Installation Procedures PN: 455-01607-001...
  • Page 2 Since implementation by customers of each product may vary, the suitability of specific product configurations and applications must be determined by the customer and is not warranted by NEC Computers Inc. To allow for design and specification improvements, the information in this document is subject to change at any time, without notice.
  • Page 3: Table Of Contents

    Express5800/120Ed Rack Mount Kit Installation Procedures CONTENTS Introduction ............................3 Unpacking and Inspection ........................4 Before You Begin...........................6 What You Need ............................6 Static Precautions ...........................6 Equipment Information...........................7 Preparing Your Server Unit ........................7 Removing the Front Bezel........................7 Removing the Side Panels........................8 Installing the LED Holder and Labels....................9 Removing a Foot Stand ........................13 Installing the New Front Bezel......................15 Installing the Side Panels .........................18...
  • Page 5: Introduction

    Introduction This guide provides you with assembly information for preparing and mounting your Express5800/120Ed Server small tower unit into a system rack (see Figure 1). Figure 1. Rack Mounted Server Small Tower Unit Express5800/120Ed Rack Mount installation Procedures 3...
  • Page 6: Unpacking And Inspection

    Unpacking and Inspection Although the rack mount kit is inspected and carefully packaged at the factory, damage may occur during shipping. Follow these steps for unpacking the kit. 1. Visually inspect the shipping container; notify your carrier immediately of any damage. 2.
  • Page 7 Express5800/120Ed Figure 2. Rack Mount Kit Parts Express5800/120Ed Rack Mount installation Procedures 5...
  • Page 8: Before You Begin

    Before You Begin Before you begin, please review the following cautions, warnings, and general guidelines. WARNING Be sure that power to the server unit is turned off and unplugged. All voltage is removed only when the power cord is unplugged. Avoid excessive vibration and shock.
  • Page 9: Equipment Information

    Equipment Information Measurements for the rack are given in Us where 1U is equal to 1.75 inches. Every three holes on the inside of the rack are equal to 1U. The height of the Server Small Tower Unit is 5Us (8.75 inches). Preparing Your Server Unit To prepare your server small tower unit for rack mounting, you must first remove the front bezel, the side panels, and the four foot stands on the bottom of...
  • Page 10: Removing The Side Panels

    Figure 3. Removing the Front Bezel Removing the Side Panels ! CAUTION If you are removing a side panel after the server unit is set up, you must first power off the system and all external devices. Unplug the system power cord To remove a side panel: 1.
  • Page 11: Installing The Led Holder And Labels

    Figure 4. Removing a Server Unit Side Panel Installing the LED Holder and Labels The Power and HDD LEDs must be removed from the LED holder currently installed on the front of the chassis and then reinserted into a new LED holder. The Status LED remains in its current LED holder and is reinserted into its original slot in the front of the chassis.
  • Page 12 Figure 5. Removing the LED Holder Assembly 5. Tag and remove the Power and HDD LEDs from the top and bottom sockets of the LED holder (see Figure 6). Power Figure 6. Removing LEDs from the LED Holder 6. Feed the Power and HDD LED cable assemblies back through the mounting hole in the front of the chassis.
  • Page 13 8. Reinsert the Power and HDD LEDs into the top and bottom sockets of the new LED holder (see Figure 7). Figure 7. Inserting the Relocated LEDs into the New LED Holder 9. Insert the bottom tab of the new LED holder into the mounting hole slot in the front of the chassis while pushing down on the top tab of the holder and snap the LED holder into place (see Figure 8).
  • Page 14 10. Reinsert the bottom tab of the original LED holder containing the Status LED back into its mounting hole slot while pushing down on the top tab of the holder and snap the LED holder into place. 11. On the front of the new bezel adhere the three new labels as shown in Figure 9A, B, and C.
  • Page 15: Removing A Foot Stand

    Removing a Foot Stand Each of the four foot stands located on the bottom of the server unit consists of a three piece assembly and are easily removed (see Figure 10). Note: Each foot stand is secured with two small screws. 1.
  • Page 16 Bottom Figure 10. Removing a Foot Stand Item Description Long Stem Nut Movable Stand Stationary Base Hex Screw Phillips Head Screw Express5800/120Ed Rack Mount installation Procedures 14...
  • Page 17: Installing The New Front Bezel

    Installing the New Front Bezel 1. Ensure that the left side panel of the server unit is removed as described earlier. 2. Position the server unit on its right side. Figure 11. Install the Front Bezel Handles 3. Install two handles onto the new front bezel with the four screws supplied. See Figure 11.
  • Page 18 Figure 12. Removing the Device Bay Door 5. Remove the three screws that secure three small brackets located at the top of the new front bezel. See Figure 13. Save the screws and brackets for use in Step 8. 6. Carefully tilt and insert the bottom tab hooks of the front bezel into the corresponding bottom tab slots in the front of the server unit (see Figure 13).
  • Page 19 Figure 13. Installing and Securing the Front Bezel 9. Locate the three screw holes underneath the bottom of the front bezel and loosen the screws (see Figure 14). Firmly hold the bottom of the bezel flush against the bottom of the server chassis and tighten the screws. This will correctly align the front bezel to the server chassis.
  • Page 20: Installing The Side Panels

    10. Reinstall the “Device Bay Door” on the front bezel and secure with the captive spring screw (see Figure 15). Figure 15. Installing the Device Bay Door 11. Install the side panel on the server unit as described later in this section. Installing the Side Panels 1.
  • Page 21: Preparing The Mounting Bracket Assemblies

    Preparing the Mounting Bracket Assemblies Your server mounts in the system rack using two rail assemblies. The left rail assembly as viewed from the front of the system rack is shown in Figure 16. Each rail assembly consists of two rack mounting brackets (A and B). These pieces can be separated and adjusted.
  • Page 22 Figure 17. Attaching the Mounting Bracket to the Front of the Rack 3. Attach the left and right rear mounting brackets to the rear of the rack using Phillips flange head screws supplied. 4. Attach the left front and rear mounting brackets to each other using three of the Phillips-head self-tapping screws and flat washers supplied.
  • Page 23: Installing The Server Into The System Rack

    Installing the Server into the System Rack This section describes how to install your rack-mount server unit into a standard EIA 19-inch rack cabinet. WARNING Your system weighs approximately 45 pounds (20.41 kg). If your system contains numerous optional boards and peripheral devices, it will weigh more.
  • Page 24 Rear vertical mounting rail Front vertical mounting rail Rack-mount server unit Four plastic washers Four screws Figure 19. Installing the Rack-Mount Server Unit into the Rack Cabinet Express5800/120Ed Rack Mount installation Procedures 22...
  • Page 25: Making Connections

    Making Connections Refer to Figure 20 and connect your keyboard, monitor, and mouse. Connect any external peripheral devices such as a printer or modem by following the instructions included with these devices. ! CAUTION Damage to the system may result if the keyboard/mouse cable is inserted or removed when power is applied to the system.
  • Page 26: Connecting The Power Cord

    Connecting the Power Cord Plug the female end of the AC power cord into the input receptacle on the rear of the power supply cage. Plug the male end of the power cord into NEMA 5- 15R outlet for 100-120 VAC or NEMA 6-15R outlet for 200-240 VAC. If the power cord supplied with the system is not compatible with the AC wall outlet in your region, obtain a suitable power cord that meets the following criteria.
  • Page 27: Powering On Your System

    Powering On Your System Power on your system as follows. 1. Make sure all external devices, such as a video display, keyboard, and mouse have been connected, and the power cords are connected. 2. Power on the video display and any other external devices. 3.