Tools

mouse need not remain connected and can be removed. Multiple keyboard,
video, and mouse connections can be provided by the use of a KVM switch in
larger system configurations.
Dedicated Ethernet hub, router, or gateway depending on the LAN topology at your
site
1.3. Tools
A number 2 Phillips screwdriver is the only tool required for installation.
Optionally, a 3-mm flat-blade screwdriver might be helpful when installing the cell
interconnect cables.

1.4. Warnings and Cautions

Observe the warnings and cautions in
warnings and cautions are included as required throughout the document.
Type of Note
Warning
Warning
Warning
Caution
1.5.

Prerequisites

Before beginning the system installation, ensure that all site-provided power sources
and cabling are in place and that the optional (but recommended) uninterruptible power
supply (UPS) is in place and functioning properly. For more information, see the System
Planning Guide.
1-2
Table 1-1

Table 1-1 Warnings and Cautions

Wear goggles or eye protection when cutting the bands that
secure shipping containers.
Do not push on the upper portion of a server cabinet, and use
caution when moving the cabinet on its casters. The cabinet
can tip over if not handled properly.
Have two people lift each cell. A fully loaded cell weighs about
45 kg (100 lb).
Wear a wrist strap connected to a ground point when
performing maintenance on the server.
when installing the system. Additional