Extreme Networks, Inc.
3585 Monroe Street
Santa Clara, California 95051
(888) 257-3000
(408) 579-2800
http://www.extremenetworks.com
Published: February 2012
Part number: 120729-00 Rev. 01

Advertisement

Table of Contents
loading

Summary of Contents for Extreme Networks BlackDiamond X8 Series

  • Page 1 BlackDiamond X8 Series Switches Hardware Installation Guide Extreme Networks, Inc. 3585 Monroe Street Santa Clara, California 95051 (888) 257-3000 (408) 579-2800 http://www.extremenetworks.com Published: February 2012 Part number: 120729-00 Rev. 01...
  • Page 2 Unified Access Architecture, Unified Access RF Manager, UniStack, XNV, the Extreme Networks logo, the Alpine logo, the BlackDiamond logo, the Extreme Turbodrive logo, the Summit logos, and the Powered by ExtremeXOS logo are trademarks or registered trademarks of Extreme Networks, Inc. or its subsidiaries in the United States and/or other countries.
  • Page 3: Table Of Contents

    Contents Preface.................................7 Audience ..................................7 Conventions ................................7 Related Publications..............................8 PART 1: ABOUT THE BLACKDIAMOND X8 SERIES SWITCHES Chapter 1: BlackDiamond X8 Series Switches ..................13 Overview of the BlackDiamond X8 Series Switches ....................13 BlackDiamond X8 Chassis .............................14 Management Ports ..............................16 Chapter 2: BlackDiamond X8 Series Modules and Fans ..............17 Overview of the BlackDiamond X8 Modules ......................17 Management Module..............................18 Redundant Management Module Activity .......................18...
  • Page 4 Contents Rack Specifications and Recommendations ....................37 Mechanical Recommendations for the Rack....................38 Protective Grounding for the Rack ......................38 Space Requirements for the Rack ......................39 Securing the Rack............................39 Evaluating and Meeting Cable Requirements ......................40 Cabling Standards............................40 Cable Labeling and Record Keeping ......................40 Cable Distances ..............................41 Installing Cable..............................42 Fiber Optic Cable .............................43...
  • Page 5 Contents Packing the Chassis for Shipping...........................89 Preparing the Chassis for Removal.........................90 Removing the Chassis from the Rack ......................90 Assembling the Shipping Container ........................91 PART 4: APPENDICES Appendix A: Safety Information......................95 Considerations Before Installing..........................96 Maintenance Safety..............................96 General Safety Precautions ...........................97 Cable Routing for LAN Systems..........................97 Installing Power Supply Units and Connecting Power....................98 Selecting Power Supply Cords ..........................99...
  • Page 6 Contents BlackDiamond X8 Series Switches Hardware Installation Guide...
  • Page 7: Preface

    See the ExtremeXOS Concepts Guide and the ExtremeXOS Command Reference Guide for information about configuring the BlackDiamond X8 series switch. NOTE If the information in an installation note or release note shipped with your Extreme Networks equipment differs from the information in this guide, follow the installation or release note. Conventions...
  • Page 8: Related Publications

    Extreme Networks Pluggable Interface Modules Installation Guide ● ExtremeXOS Hardware and Software Compatibility Matrix Hardware and software documentation for Extreme Networks products is available from the Extreme Networks website at the following location: http://www.extremenetworks.com/go/documentation You can download software concepts guides and reference guides, hardware installation guides, and other documents.
  • Page 9 Related Publications To request an eSupport user name and password, select the Request Web Login link on the eSupport home page at: https://esupport.extremenetworks.com You can see complete information about all of our services online at: http://www.extremenetworks.com/solutions/service-solutions.aspx BlackDiamond X8 Series Switches Hardware Installation Guide...
  • Page 10 Preface BlackDiamond X8 Series Switches Hardware Installation Guide...
  • Page 11 About the BlackDiamond X8 Series Switches P A R T...
  • Page 13: Chapter 1: Blackdiamond X8 Series Switches

    BlackDiamond X8 Series Switches C H A P T E R This chapter includes the following sections: Overview of the BlackDiamond X8 Series Switches on page 13 ● BlackDiamond X8 Chassis on page 14 ● Management Ports on page 16 ●...
  • Page 14: Blackdiamond X8 Chassis

    Chapter 1: BlackDiamond X8 Series Switches BlackDiamond X8 Chassis The BlackDiamond X8 switch chassis (Figure 1) has the following physical features: Height of 14.5 RU, allowing three switches to be installed in a 7-foot rack ● Optional mid-mount brackets for flexibility in rack positioning ●...
  • Page 15 BlackDiamond X8 Chassis The front of the chassis provides access to: Card cage for the management modules and I/O modules ● Bays for redundant power supplies, with ventilated cover ● Connection point for ESD-preventive strap ● Figure 2 shows the back of the BlackDiamond X8 chassis. Figure 2: Back of the BlackDiamond X8 Chassis 1 = Grounding point 2 = ESD jack...
  • Page 16: Management Ports

    Chapter 1: BlackDiamond X8 Series Switches Management Ports Each BlackDiamond management module (MM) has a 10/100/1000BASE-TX Ethernet management port. This port allows you to communicate directly with the central processing unit (CPU) of the switch. You can plug an Ethernet cable directly from your laptop into the management port for direct access into the switch.
  • Page 17: Chapter 2: Blackdiamond X8 Series Modules And Fans

    BlackDiamond X8 Series Modules and Fans C H A P T E R This chapter includes the following sections: Overview of the BlackDiamond X8 Modules on page 17 ● Management Module on page 18 ● I/O Modules on page 21 ●...
  • Page 18: Management Module

    Chapter 2: BlackDiamond X8 Series Modules and Fans Management Module The BlackDiamond X8 series switch has two dedicated management module slots, labeled A and B, for the BDX-MM1 management module. One management module is required for switch operation; however, adding a second management module increases system availability through redundancy. Each management module contains a temperature sensor, nonvolatile random-access memory (NVRAM), and a real-time clock.
  • Page 19 Management Module Console port—The RJ-45 serial console port is used to connect a terminal, allowing you to perform ● local management. Auxiliary (AUX) port—For future development ● Management modules have the following LEDs (see Table Presence of system errors (ERR) ●...
  • Page 20: Management Module Leds

    Chapter 2: BlackDiamond X8 Series Modules and Fans Management Module LEDs LEDs on the management module (Table 4) provide status information about operation of the switch and major chassis components. Table 4: LEDs on the BDX-MM1 Management Module Label/Function Color/State Meaning Amber/steady A critical software error has been logged since power-up.
  • Page 21: I/O Modules

    For information about the LEDs and their activity on the BDXA-10G48X modules, see “I/O Module LEDs” on page 24. For information about the SFP+ modules, see the Extreme Networks Pluggable Interface Modules Installation Guide. BlackDiamond X8 Series Switches Hardware Installation Guide...
  • Page 22: Blackdiamond Bdxa-40G24X I/O Module

    For information about the LEDs and their activity on the BDXA-40G24X modules, see “I/O Module LEDs” on page 24. For information about the QSFP+ modules, see the Extreme Networks Pluggable Interface Modules Installation Guide. NOTE The BDXA-40G24X module requires BDX-FM20T fabric modules in order to function.
  • Page 23: Blackdiamond Bdxa-40G12X I/O Module

    For information about the LEDs and their activity on the BDXA-40G12X modules, see “I/O Module LEDs” on page 24. For information about the QSFP+ modules, see the Extreme Networks Pluggable Interface Modules Installation Guide. BlackDiamond X8 Series Switches Hardware Installation Guide...
  • Page 24: I/O Module Leds

    Chapter 2: BlackDiamond X8 Series Modules and Fans I/O Module LEDs LEDs on the front panel of the BlackDiamond X8 series I/O modules (Table 5) provide information about the operating status of the module and ports. Table 5: LEDs on the BlackDiamond X8 Series I/O Modules Type Label/Function Color/State...
  • Page 25: Fabric Modules

    Fabric Modules Fabric Modules Up to four fabric modules (Figure 7) can be installed in each BlackDiamond X8 chassis to provide the active switching fabric for the switch. The switch fabric supports N+1 redundancy. Three fabric modules are required to provide full switch fabric capacity. The fourth module provides excess capacity but is not required to maintain full line rate on the front-panel ports.
  • Page 26: Fan Trays

    Chapter 2: BlackDiamond X8 Series Modules and Fans Fan Trays At the back of the BlackDiamond X8 chassis are five vertical fan trays, each holding six fans (Figure Fan trays are hot-swappable. Two pairs of LEDs on each fan tray indicate operating status for the fabric module installed behind that fan tray (Table 6 on page 25) and for the fan tray...
  • Page 27: Chapter 3: Power Supplies For The Blackdiamond X8 Switch

    Power Supplies for the BlackDiamond X8 Switch C H A P T E R This chapter includes the following sections: Overview of the BlackDiamond X8 Series Power Supplies on page 27 ● AC Power Supply on page 28 ● WARNING! Field operators must not attempt to open the power supply enclosure for any reason;...
  • Page 28: Ac Power Supply

    Chapter 3: Power Supplies for the BlackDiamond X8 Switch AC Power Supply The AC power supply for the BlackDiamond X8 switch (Figure 9) delivers 2500 W when operated from 185 to 264 V AC, or 1250 W when operated from 90 to 140 V AC. Figure 9: BlackDiamond X8 AC Power supply 1 = LEDs 2 = Release button...
  • Page 29: Fuse

    An AC power cord is not included with the BlackDiamond X8 AC power supply. You can purchase AC power cords for use in the US and Canada from Extreme Networks or from your local supplier. An AC power cord for use with the BlackDiamond X8 AC power supply must meet the requirements listed in “Power Cord Requirements”...
  • Page 30 Chapter 3: Power Supplies for the BlackDiamond X8 Switch BlackDiamond X8 Series Switches Hardware Installation Guide...
  • Page 31: Part 2: Hardware Installation

    Hardware Installation P A R T...
  • Page 33: Chapter 4: Site Preparation

    Site Preparation C H A P T E R This chapter includes the following sections: Planning Your Site on page 33 ● Meeting Site Requirements on page 34 ● Evaluating and Meeting Cable Requirements on page 40 ● Meeting Power Requirements on page 44 ●...
  • Page 34: Meeting Site Requirements

    ● After examining your physical site and verifying that all environment requirements are met, evaluate and compare your existing cable plant with the requirements of the Extreme Networks equipment to determine if you need to install new cables. Meeting power requirements ●...
  • Page 35 Meeting Site Requirements Table 9: Authorities on Electrical Codes Organization Address Web Site URL National Electrical Code (NEC) Classification (USA only) NFPA http://www.nfpa.org 1 Batterymarch Park Recognized authority on safe electrical wiring. Federal, Quincy, Massachusetts state, and local governments use NEC standards to 02169 establish their own laws, ordinances, and codes on wiring specifications.
  • Page 36: Wiring Closet Considerations

    Temperature Extreme Networks equipment generates a significant amount of heat. It is essential that you provide a temperature-controlled environment for both performance and safety. Install the equipment only in a temperature- and humidity-controlled indoor area that is free of airborne materials.
  • Page 37: Humidity

    Meeting Site Requirements Humidity To maximize equipment life, keep operating humidity between 50% and 70% relative humidity (non-condensing) during typical operation. The equipment can operate between 10% and 95% relative humidity (non-condensing) for short intervals. Chassis Airflow Requirements To ensure proper airflow through a BlackDiamond switch, refer to the following recommendations when you install the switch: For proper airflow, BlackDiamond X8 series switches require a minimum of 24 inches (61 cm) ●...
  • Page 38: Mechanical Recommendations For The Rack

    Use a rack grounding kit and a ground conductor that is carried back to earth or to another suitable building ground. All Extreme Networks switches are designed with mounting brackets that provide solid metal-to-metal connection to the rack. If you do not use equipment racks, you can attach wiring terminals directly to the mounting brackets for appropriate grounding.
  • Page 39: Space Requirements For The Rack

    Meeting Site Requirements Space Requirements for the Rack Provide enough space in front of and behind the switch so that you can service it easily. Allow a minimum of 48 inches (122 cm) in front of the rack and 24 inches (61 cm) behind the rack. When using a relay (two-post) rack, provide a minimum of 24 inches (61 cm) of space behind the mounted equipment.
  • Page 40: Evaluating And Meeting Cable Requirements

    Assign a unique block of sequential numbers to the group of cables that run between each pair of ● wiring closets. Assign a unique identification number to each distribution rack. ● Identify all wiring closets by labeling the front panel of your Extreme Networks equipment and ● other hardware. Keep accurate and current cable identification records. ●...
  • Page 41: Cable Distances

    (850 nm optical window) 50 m multimode fiber (OM4) 150 meters a.Proprietary to Extreme Networks. Connections between two Extreme Networks 1000BASE-LX interfaces that use 10/125 μm single-mode fiber can use a maximum distance of 10,000 meters. BlackDiamond X8 Series Switches Hardware Installation Guide...
  • Page 42: Installing Cable

    Chapter 4: Site Preparation Table 11: Extreme Networks Direct-Attach Cables Cable Type Model Number Length SFP+ passive copper cable 10304 1 meter 10305 3 meters 10306 5 meters 10307 10 meters QSFP+ passive copper cable 10311 0.5 meter 10312 1 meter...
  • Page 43: Fiber Optic Cable

    It is also important not to stretch the cable during installation. Extreme Networks recommends that the bend radius for fiber optic cable equal 2 inches (5.08 cm) minimum for each 90 degree turn as shown in...
  • Page 44: Meeting Power Requirements

    In regions that are susceptible to electrical storms, Extreme Networks recommends that you plug ● your system into a surge suppressor.
  • Page 45: Ac Power Cord Requirements

    AC power input cords are not provided with BlackDiamond power supplies. To purchase a power cord for your product and for your specific country, contact your local Extreme Networks Channel Account Manager or Sales Manager, or purchase a cord from your local supplier.
  • Page 46: Calculating Volt-Amperage Requirements

    UPS Transition Time Transition time is the time that is necessary for the UPS to transfer from utility power to full-load battery power. For Extreme Networks products, a transition time of less than 20 milliseconds is required for optimum performance.
  • Page 47: Chapter 5: Installing A Blackdiamond X8 Series Chassis

    Installing a BlackDiamond X8 Series Chassis C H A P T E R This chapter provides instructions for installing the BlackDiamond X8 chassis in an equipment rack. The BlackDiamond X8 chassis is designed to fit into a standard 19-inch equipment rack. Optional mid-mount brackets allow you to install the chassis in a mid-mount position.
  • Page 48 Chapter 5: Installing a BlackDiamond X8 Series Chassis Refer to the illustrations printed on the BlackDiamond X8 shipping container and unpack the chassis and accessories as follows: 1 Cut the straps around the box (Figure 13). Figure 13: Unstrapping the Box 2 Slide the box up and off the chassis and interior packing foam (Figure 14).
  • Page 49 Unpacking the Chassis 3 Remove the support brackets and boxed accessories and set them aside until you need them (Figure 15). 4 Lift off the upper packing foam. Pull apart the keyed corner of the lower packing foam and remove the lower packing foam from around the chassis (Figure 15).
  • Page 50: Pre-Installation Requirements

    Save all packaging, bolts, and washers, as well as the box and pallet, for future use in the event that the chassis must be moved to another location or returned to Extreme Networks. Verify that the following items are included in the shipping carton: BlackDiamond X8 chassis with installed front shipping cover and MM slot cover ●...
  • Page 51: Rack-Mounting The Chassis

    Rack-Mounting the Chassis Screwdriver appropriate for the selected rack mounting screws ● Chassis grounding materials as listed on page ● Before you install the chassis, verify that none of the modules or power supplies have been pre-installed. Because of the weight of the BlackDiamond X8 chassis, it should be empty when you install it.
  • Page 52 Chapter 5: Installing a BlackDiamond X8 Series Chassis 2 Identify the rack location where the chassis will be installed. 3 Using four rack mounting screws, attach the support bracket to the equipment rack immediately below the intended chassis location (Figure 19).
  • Page 53 Rack-Mounting the Chassis 7 Secure the chassis to the equipment rack using six rack mounting screws. (Screws are not provided.) Be sure that the screws are secure. Refer to Figure 20 for the screw locations. Figure 20: Securing the Chassis to the Rack After the chassis is secured to the equipment rack, ground the chassis as described in the next section.
  • Page 54: Grounding The Chassis

    Chapter 5: Installing a BlackDiamond X8 Series Chassis Grounding the Chassis Although grounding the BlackDiamond X8 series chassis is optional, it is recommended to do so. The rear panel of the chassis provides a grounding pad with threaded holes for attaching a ground cable. You must provide the following materials to ground the chassis: Two 10-24 screws ●...
  • Page 55 Installing Power Supplies To install a power supply: 1 Remove the power supply ventilation cover as follows: a Loosen the retaining screws at the top corners of the cover panel. b Pull outward on the retaining screws to tilt the cover panel away from the front of the chassis. c Lift the cover panel away from the chassis.
  • Page 56 Chapter 5: Installing a BlackDiamond X8 Series Chassis 4 Slide the power supply into the chassis until the lever starts to engage (Figure Figure 24: Installing a Power Supply 5 Rotate the lever toward the front of the power supply to fully seat the power supply in the chassis. 6 Repeat steps through to install other power supplies as required by your system configuration.
  • Page 57 Installing Power Supplies Figure 25: Installing the Power Supply Ventilation Cover BlackDiamond X8 Series Switches Hardware Installation Guide...
  • Page 58: Connecting Power

    Chapter 5: Installing a BlackDiamond X8 Series Chassis Connecting Power To connect power to the BlackDiamond X8 chassis: 1 At the back of the chassis, connect an AC power cord to the power input socket that corresponds to each installed power supply. Power input sockets are numbered from 1A to 8B from left to right, as you face the chassis back (Figure 26).
  • Page 59: Chapter 6: Installing Blackdiamond X8 Series Modules

    Installing BlackDiamond X8 Series Modules C H A P T E R This chapter provides instructions to install system modules in the BlackDiamond X8 switch and includes the following sections: Installation Order on page 59 ● Installing Fabric Modules on page 60 ●...
  • Page 60: Installing Fabric Modules

    Chapter 6: Installing BlackDiamond X8 Series Modules Installing Fabric Modules The slots for fabric modules are numbered 1 through 4, from left to right. If you are installing only three fabric modules, use slots 1 through 3. Install all the fabric modules before you install I/O modules. To install fabric modules: 1 Attach the ESD-preventive wrist strap to your bare wrist.
  • Page 61 Installing Fabric Modules 3 Install each fabric module: a Loosen the screws on the insertion/extraction levers and open the levers (Figure 29). Figure 29: Installing a Fabric Module b Align the circuit board with the guides at the top and bottom of the chassis and slide the module into the chassis.
  • Page 62 Chapter 6: Installing BlackDiamond X8 Series Modules d Align and tighten the retaining screws to fasten the module in place (Figure 30). Figure 30: Securing a Fabric Module 4 Repeat these steps to install additional fabric modules. BlackDiamond X8 Series Switches Hardware Installation Guide...
  • Page 63 Installing Fabric Modules 5 Re-install the removed fan trays: a Set each fan tray into the chassis and push it firmly into place (Figure 31). b Align and tighten the retaining screws. Figure 31: Installing a Fan Tray BlackDiamond X8 Series Switches Hardware Installation Guide...
  • Page 64: Installing Management Modules

    Chapter 6: Installing BlackDiamond X8 Series Modules Installing Management Modules Slots for management modules are labeled A and B. Install the first management module in slot A. To install a management module: 1 Attach the ESD-preventive wrist strap to your bare wrist. If it is not already connected, connect the metal end to the receptacle between the management module slots.
  • Page 65: Installing I/O Modules

    Extreme Networks. 2 Attach the ESD-preventive wrist strap to your bare wrist. If it is not already connected, connect the metal end to the receptacle between the management module slots.
  • Page 66 Chapter 6: Installing BlackDiamond X8 Series Modules 4 Verify that the module injector/ejector handles are open (Figure 34). Keep the injector/ejector handles in the open position as you slide the module into the chassis slot. NOTE If the injector/ejector handles are in the latched position, they prevent the module from sliding all the way into the slot.
  • Page 67: I/O Module Blanks

    I/O Module Blanks 7 Use a # 2 Phillips screwdriver to lock each handle into place (Figure 35). When a locking screw is fully tightened, the yellow band around the screw head is completely hidden. CAUTION Be careful to avoid over-torquing and stripping the screw heads. Figure 35: Locking the Module into Place I/O Module Blanks BlackDiamond X8 switches are shipped with a reinforcement shipping cover installed over all the I/O...
  • Page 68: Installing A Module Blank

    Chapter 6: Installing BlackDiamond X8 Series Modules Installing a Module Blank To install a module blank: 1 Check the condition of the EMI gaskets along the front panel edges of the blank, and confirm that the gaskets are not damaged. 2 Align the module blank with the card guides for the open slot on the chassis (see Figure 36).
  • Page 69: Initial Management Access

    ● Flow control—XON/XOFF ● The terminal or PC with terminal-emulation software that you connect to an Extreme Networks switch must be configured with these settings. This procedure is described in the documentation supplied with the terminal. Appropriate cables are available from your local supplier, or you can make your own. To ensure the electromagnetic compatibility of the unit, use only shielded serial cables.
  • Page 70 Chapter 6: Installing BlackDiamond X8 Series Modules 5 At the password prompt, press [Return]. The default user name admin has no password assigned to it. When you have successfully logged on to the system, the command line prompt displays the system name (for example, BlackDiamondX8>...
  • Page 71: Part 3: Maintenance Procedures

    Maintenance Procedures P A R T...
  • Page 73: Chapter 7: Blackdiamond X8 Maintenance Procedures

    BlackDiamond X8 Maintenance Procedures C H A P T E R This chapter provides instructions for maintenance procedures for the BlackDiamond X8 switch and includes the following sections: Replacing a Power Supply on page 74 ● Replacing a Fan Tray on page 76 ●...
  • Page 74: Replacing A Power Supply

    Chapter 7: BlackDiamond X8 Maintenance Procedures Replacing a Power Supply You need a #2 Phillips screwdriver to remove the power supply ventilation cover. To replace a power supply: 1 Remove the power supply ventilation cover (Figure 37). a Loosen the retaining screws at the top corners of the cover panel. b Pull outward on the retaining screws to tilt the cover panel away from the front of the chassis.
  • Page 75 Replacing a Power Supply Figure 38: Removing a Power Supply 5 On the front of the replacement power supply, push the release button for the insertion/ejector lever. 6 Slide the power supply into the chassis until the lever starts to engage (Figure 39).
  • Page 76: Replacing A Fan Tray

    Chapter 7: BlackDiamond X8 Maintenance Procedures 8 Replace the power supply ventilation cover as follows: a Set the lower edge of the cover in place so that the tabs on the edge fit into the matching slots in the chassis frame (Figure 40).
  • Page 77 Replacing a Fan Tray Figure 41: Removing a Fan Tray 3 Holding the replacement fan tray with both handles, align it with the opening and slide it straight into the chassis (Figure 42). 4 Align and tighten the retaining screws. Figure 42: Installing a Fan Tray BlackDiamond X8 Series Switches Hardware Installation Guide...
  • Page 78: Replacing A Fabric Module

    Chapter 7: BlackDiamond X8 Maintenance Procedures Replacing a Fabric Module You need a the following tools to replace a fabric module: ESD-preventive wrist strap ● #2 Phillips screwdriver for the retaining screws on the fan tray ● 5/16-inch flat-tip screwdriver for the retaining screws on the fabric module ●...
  • Page 79 Replacing a Fabric Module 3 Remove the fabric module: a Loosen the retaining screw on each inserter/extractor lever on the fabric module (Figure 44). b Simultaneously rotate both levers toward the ends of the module to unseat the internal connectors (Figure 44).
  • Page 80 Chapter 7: BlackDiamond X8 Maintenance Procedures c Carefully slide the module out of the switch chassis (Figure 45) and set it aside on an anti-static surface. Figure 45: Removing a Fabric Module 4 Install the replacement fabric module: a Remove the module from the antistatic packaging. a Loosen the screws on the insertion/extraction levers and open the levers.
  • Page 81 Replacing a Fabric Module Figure 46: Installing a Fabric Module c When the levers start to engage, push them toward the module to seat the module in the chassis. d Align and tighten the retaining screws to fasten the module in place. Figure 47: Securing a Fabric Module BlackDiamond X8 Series Switches Hardware Installation Guide...
  • Page 82: Replacing A Management Module

    Chapter 7: BlackDiamond X8 Maintenance Procedures 5 Re-install the removed fan tray: a Set the fan tray into the chassis and push it firmly into place. b Align and tighten the retaining screws. Figure 48: Installing a Fan Tray Replacing a Management Module You need the following tools and equipment to replace a BlackDiamond X8 series management module: ESD-preventive wrist strap ●...
  • Page 83 Replacing a Management Module 3 On the injector/ejector lever, turn the captive screw counter-clockwise until the yellow band around the screw head of is completely visible (Figure 49). Figure 49: Unlocking a Module 4 Squeeze the release latch on the injector/ejector handle and rotate the handle to the right (away from the module) to unseat the module from the internal connectors (Figure 50).
  • Page 84: Installing A Management Module

    Chapter 7: BlackDiamond X8 Maintenance Procedures Installing a Management Module To install the replacement management module: 1 Remove the module from the antistatic packaging. CAUTION To prevent ESD damage, hold the module by the metal rail and front panel only. Never touch the components on the PCB or the pins on any of the connectors.
  • Page 85: Installing A Management Module Blank

    Replacing a Management Module Figure 52: Locking the Module into Place Installing a Management Module Blank If a management module is not installed in a slot, you must install a blank cover over the slot to maintain proper EMI levels and ventilation to ensure conformance to FCC requirements as well as to maintain adequate airflow through the switch.
  • Page 86: Replacing An I/O Module

    Chapter 7: BlackDiamond X8 Maintenance Procedures Replacing an I/O Module You need the following tools and equipment to replace a BlackDiamond X8 series module: ESD-preventive wrist strap ● #2 Phillips screwdriver ● Module blank panel if you are not replacing the module ●...
  • Page 87: Installing An I/O Module

    Replacing an I/O Module 5 Slide the module out of the chassis slot. 6 Immediately place the module into an anti-static bag to protect it from potential ESD damage. The bag will also prevent dust from collecting on the module connectors. 7 If you are not going to install a replacement module, install a blank front panel as described in “Installing I/O Module Blanks”...
  • Page 88: Installing I/O Module Blanks

    Chapter 7: BlackDiamond X8 Maintenance Procedures 4 Push the handles toward each other to seat the internal module connectors. 5 Use a # 2 Phillips screwdriver to lock each handle into place (Figure 56). When a locking screw is fully tightened, the yellow band around the screw head is completely hidden.
  • Page 89: Packing The Chassis For Shipping

    Packing the Chassis for Shipping This section describes how to pack the BlackDiamond X8 chassis for shipment back to Extreme Networks. You need the following tools and materials to pack a BlackDiamond X8 series chassis: Original shipping cover for the front module slots ●...
  • Page 90: Preparing The Chassis For Removal

    Chapter 7: BlackDiamond X8 Maintenance Procedures Preparing the Chassis for Removal To prepare the chassis for removal from the rack, remove the installed modular components: 1 Turn off the power to the chassis and remove the installed power supplies. a Remove the power cord retainer and disconnect all power cords. b Remove all the installed power supplies as described on page 2 Remove all the installed modules.
  • Page 91: Assembling The Shipping Container

    Packing the Chassis for Shipping Assembling the Shipping Container To assemble the shipping container for the BlackDiamond X8 chassis: 1 At each corner, attach a restraining bolt to the shipping bracket, securing the BlackDiamond X8 chassis to the shipping pallet (see Figure 59).
  • Page 92 Chapter 7: BlackDiamond X8 Maintenance Procedures 3 Set a corner brace at each corner of the chassis, and slide the shipping carton down over the chassis (Figure 61). Figure 61: Placing the Shipping Carton over the Chassis 4 Secure the carton to the pallet using nylon strapping (Figure 62).
  • Page 93: Part 4: Appendices

    Appendices P A R T...
  • Page 95: Appendix A: Safety Information

    Only trained and qualified service personnel (as defined in IEC 60950-1) should install, replace, or perform service to Extreme Networks switches and their components. Qualified personnel have read all related installation manuals, have the technical training and experience necessary to be aware of the hazards to which they are exposed in performing a task, and are aware of measures to minimize the danger to themselves or other persons.
  • Page 96: Considerations Before Installing

    ● supply, module, or other component. In the event of failure, return the defective unit to Extreme Networks for repair or replacement, unless otherwise instructed by an Extreme Networks representative. To remove power from the system, you must unplug all power cords from wall outlets. The power ●...
  • Page 97: General Safety Precautions

    Cable Routing for LAN Systems Extreme Networks equipment meets the requirements for LAN system equipment. LAN systems are designed for intra-building installations; that is, cable runs between devices must be in the same building as the connected units, except under the conditions listed in the next paragraph.
  • Page 98: Installing Power Supply Units And Connecting Power

    If a single power source fails, it will affect only that power supply to which it is connected. Extreme Networks AC power supplies do not have switches for turning the unit on and off. Remove ●...
  • Page 99: Selecting Power Supply Cords

    Selecting Power Supply Cords Extreme Networks does not provide power input cords in the product box. To purchase a power cord for your product and for your specific country, contact your local Extreme Networks Channel Account Manager or Sales Manager, or purchase a cord from your local supplier. Requirements for the power...
  • Page 100: Gbic, Sfp (Mini-Gbic), Qsfp+, Xenpak, And Xfp Regulatory Compliance

    Extreme Networks optical modules are tested to work in all supported Extreme Networks switches. We recommend that all customers use Extreme Networks optical modules in their Extreme Networks switches. Extreme Networks assumes no liability for third-party optical modules. Although Extreme Networks does not block third-party optical modules, we cannot ensure that all third-party optical modules operate properly in all Extreme Networks switches.
  • Page 101: Berlegungen Vor Der Installation

    Versichern Sie sich, dass Ihre Netzteile den Gleichstrom- bzw. Wechselstrombedarf aller ● Netzwerkgeräte decken können. Racks für Extreme Networks-Geräte müssen fest am Boden verankert werden. Bei nicht ● vorschriftsmäßiger Fixierung des Racks besteht die Gefahr, dass das Rack bei Wartungsarbeiten umkippt.
  • Page 102: Allgemeine Sicherheitshinweise

    ● Netzteil, Modul oder andere Komponenten eigenmächtig zu reparieren. Senden Sie im Falle einer Störung das defekte Teil zur Reparatur oder zum Austausch an Extreme Networks ein, sofern ein Extreme Networks-Vertreter nicht etwas anderes angibt. Um das System spannungslos zu machen, müssen Sie alle Netzkabel aus den Netzsteckdosen ziehen.
  • Page 103 Zugentlastungsvorrichtungen. Kabelverlegung für LAN-Systeme Extreme Networks-Geräte erfüllen die Anforderungen für Geräte für LAN-Systeme. LAN-Systeme sind für gebäudeinterne Installationen konzipiert, das heißt, die Kabel zwischen den einzelnen Einheiten müssen im gleichen Gebäude verlaufen, in dem auch die Geräte untergebracht. Hiervon ausgenommen sind nur die unten aufgeführten Bedingungen.
  • Page 104: Installation Der Netzteile Und Netzanschluss

    ● vom Nutzer zu warten sind. Senden Sie im Falle einer Störung das defekte Netzteil zur Reparatur oder zum Austausch an Extreme Networks ein. Fassen Sie nicht mit der Hand in einen offenen Netzteileinschub, wenn das Netzteil entfernt wurde. ●...
  • Page 105: Auswahl Der Netzkabel

    Bereich kann beispielsweise nur mithilfe eines Spezialwerkzeugs, Schloss und Schlüssel oder einer anderen Sicherheitsvorrichtung geöffnet werden. HINWEIS Da die Gebäudevorschriften in aller Welt unterschiedlich sind, empfiehlt Extreme Networks dringend, sich bezüglich der korrekten Erdung und Spannungsverteilung für Ihre Installation in Ihrem Land an einen Elektrofachbetrieb zu wenden.
  • Page 106: Wechseln Und Entsorgen Der Batterie

    Die Batterien in Extreme Produkten sind gekapselt und dürfen nur durch qualifiziertes Extreme-Wartungspersonal ausgewechselt werden. Wenden Sie sich für den Austausch eines Produktes an das Wartungspersonal von Extreme Networks. Versuchen Sie nicht, die Batterie selbst auszuwechseln. Bei einer Missachtung dieser Anweisungen und dem Versuch, die Batterien eigenmächtig zu wechseln, müssen folgende Richtlinien eingehalten werden, um eine mögliche...
  • Page 107 Fiber Optic Ports and Optical Safety Konformität von GBIC, SFP (Mini-GBIC), QSFP+, XENPAK und XFP Steckbare optische Module von Extreme Networks und direkt angeschlossene Kabel erfüllen folgende gesetzliche Vorschriften: Laserprodukt der Klasse 1 oder Klasse 1M ● EN60825-1:2007 2. Ausgabe oder später, Europäische Norm ●...
  • Page 108 Appendix A: Safety Information BlackDiamond X8 Series Switches Hardware Installation Guide...
  • Page 109: Appendix B: Technical Specifications

    Technical Specifications A P P E N D I X This appendix contains the following specifications: BlackDiamond X8 Switch on page 109 ● Modules for BlackDiamond X8 Switches on page 112 ● Power Supplies for BlackDiamond X8 Switches on page 113 ●...
  • Page 110: Appendix B: Technical Specifications

    Appendix B: Technical Specifications Table 12: BlackDiamond X8 Switch Technical Specifications (Continued) Safety Standards North American UL 60950-1:2007 2nd Ed. or UL 60950-1 1st Ed:2007 as applicable (US) cULus listed to CSA 22.2 No. 60950-1-07 (Canada) FCC 21 CFR 1040.10 (US Laser Safety) CDRH Letter of Approval (US FDA Approval) European/International CB Scheme, IEC 60950-1:2005, 2nd Ed.
  • Page 111 BlackDiamond X8 Switch Table 12: BlackDiamond X8 Switch Technical Specifications (Continued) Environmental Data Operating conditions Operating temperature range: 0° C to 40° C (32° F to 104° F) Operating humidity: 10% to 93% relative humidity, non-condensing Operational shock: 30 m/s (3 g), 11 ms, 60 shocks Operational sine vibration: 5 to 100 to 5 Hz @ 0.2 g, 0 to peak, 0.1 oct./min.
  • Page 112: Modules For Blackdiamond X8 Switches

    Appendix B: Technical Specifications Modules for BlackDiamond X8 Switches Table 13: Specifications for BlackDiamond X8 Series Modules I/O Modules Dimensions 3 inches high by 17 inches wide by 18 inches deep (all models) (7.6 cm x 43.1 cm x 45.7 cm) Note: Inserter/extractor levers add 2.25 inches (5.7 cm) to the depth measurement.
  • Page 113: Power Supplies For Blackdiamond X8 Switches

    Power Supplies for BlackDiamond X8 Switches Power Supplies for BlackDiamond X8 Switches Table 14: Specifications for the BlackDiamond X8 AC Power Supply (Model # 48011) Typical configuration 3 power supplies Full configuration 8 power supplies Physical characteristics Height: 1.5 inches (3.8 cm) Width: 4.2 inches (10.6 cm) Depth: 14.5 inches (36.8 cm) Weight: 5.3 lb (2.4 kg)
  • Page 114: Connector Pinouts

    Appendix B: Technical Specifications Connector Pinouts Table 15 shows the pinouts for the RJ-45 console port on the BlackDiamond X8 switch. Table 15: RJ-45 Console Port on BlackDiamond X8 Switch Function Pin Number Direction CTS (clear to send) DTR (data carrier detect) TXD (transmit data) GND (ground) —...
  • Page 115: Conformity Statements For Emc Class A

    Conformity Statements for EMC Class A Figure 64 shows the pinouts for a 9-pin to 9-pin (PC-AT) null-modem serial cable. Figure 64: PC-AT Serial Null-modem Cable Pinouts Switch PC-AT Serial Port Cable connector: 9-pin female Cable connector: 9-pin female Screen Shell Shell Screen...
  • Page 116: Class A Notice For Taiwan

    Appendix B: Technical Specifications Class A Notice for Taiwan WARNING! This is a Class A product. In a residential environment this product may cause radio interference, in which case the user may be required to take appropriate measures. WARNING! WARNING! Japan (VCCI Class A) This is a Class A product based on the standard of the VCCI Council.
  • Page 117: Index

    Index slack, 42 types and distances, 41 AC power cord, 29 cable labeling, 40 AC power supply cabling standards features, 28 ANSI, 46 LEDs, 28 BICSI, 40 acoustic sound specifications, 111 capacity, switch fabric, 25 amperage, calculating for UPS, 46 category 5 cable, 42 ANSI standards, 46 chassis...
  • Page 118 Index temperature, 36 installation wiring closet, 36 chassis, 51 equipment rack fabric modules, 60 grounding, 38 fan tray, 76 mechanical recommendations, 38 I/O modules, 65 mounting holes, 38 management modules, 64 securing, 39 module blank, 68, 88 service access, 39 power supply, 55 space requirements, 39 IP settings, configuring, 69...
  • Page 119 Index ports standards console, 19 cabling, 40, 46 console port settings, 69 commercial building, 46 management, 16, 18 grounding, 46 power cord rack, 37 obtaining, 29 storage conditions, 111 requirements, 45 support bracket, 52 power requirements switch configuration, saving, 18 power cord, 45 switch fabric capacity, 25 power supplies...
  • Page 120 Index wiring closet airflow requirements, 37 electrostatic discharge, 37 floor coverings, 36 grounding, 36 humidity, 37 rack, securing, 39 temperature, 36 BlackDiamond X8 Series Switches Hardware Installation Guide...

Table of Contents