a *1
G
600
16
(23.6)
(.6)
G
DKU
36
Maximum Configuration Service Clearance
G
G
600
600
(23.6)
(23.6)
G
G
DKU
DKU
1. Clearance (a+b) depends on the floor load rating and clearance C. Floor
load ratings are shown below.
4350(171.3)
G
G
718
600
(28.3)
(23.6)
G
G
Front
DKC
DKU
Floor cutout area for cables
Screw jack
Caster
Service clearance
G
Grid panel(Perforated tile) should be at
least 450mm(17.7") x 450mm(17.7")
HP SureStore E Disk Array XP512: Site Prep Guide
(Unit: mm(inches))
b *1
G
G
600
600
16
(23.6)
(23.6)
(.6)
G
G
DKU
DKU
800
(31.5)
2400
800
(94.5)
(31.5)
800
(31.5)
C *1
Need help?
Do you have a question about the StorageWorks XP512 - Disk Array and is the answer not in the manual?
Questions and answers