Emerson Liebert NX 10-30kVA Installation Manual

Emerson Liebert NX 10-30kVA Installation Manual

Liebert nx series 10-30kva, 208v, 60hz
Table of Contents

Advertisement

Liebert NX
UPS
Installation Manual–10-30kVA, 208V, 60Hz
AC Power
For Business-Critical Continuity

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the Liebert NX 10-30kVA and is the answer not in the manual?

Questions and answers

Summary of Contents for Emerson Liebert NX 10-30kVA

  • Page 1 Liebert NX ™ Installation Manual–10-30kVA, 208V, 60Hz AC Power For Business-Critical Continuity...
  • Page 3: Table Of Contents

    MPORTANT AFETY NSTRUCTIONS ............3 LOSSARY OF YMBOLS .
  • Page 4 External Battery Cabinet Installation ......... . 20 3.4.1 Matching Battery Cabinets .
  • Page 5 NSTALLATION RAWINGS PECIFICATIONS AND Lug Size and Torque Requirements ..........59 Cable Lengths: Floor to Connection Point Inside UPS .
  • Page 6 Table 1 Input dry contacts at X3 ............15 Table 2 Maintenance bypass cabinet interface.
  • Page 7: Save These Instructions

    MPORTANT AFETY NSTRUCTIONS SAVE THESE INSTRUCTIONS This manual contains important instructions that should be followed during installation of your Liebert NX™ UPS and batteries. Read this manual thoroughly, paying special attention to the sections that apply to your installation, before working with the UPS. Retain this manual for use by installing personnel. WARNING Exercise extreme care when handling UPS cabinets to avoid equipment damage or injury to personnel.
  • Page 8: Battery Cabinet Precautions

    CAUTION This equipment is fitted with RFI suppression filters. Ground leakage current exceeds 3.5 mA and is less than 1000 mA. Transient and steady-state ground leakage currents, which may occur when starting the equipment, should be taken into account when selecting instantaneous residual current circuit breakers (RCCBs) or residual current devices (RCDs).
  • Page 9: Glossary Of Symbols

    LOSSARY OF YMBOLS Risk of electrical shock Indicates caution followed by important instructions AC input AC output Requests the user to consult the manual Indicates the unit contains a valve-regulated lead acid battery PbH2SO4 Recycle DC voltage Equipment grounding conductor Bonded to ground AC voltage...
  • Page 10: Installation

    NSTALLATION The Liebert NX™ UPS is designed primarily for telecommunications and data processing applica- tions. Liebert Corporation neither recommends nor knowingly sells this product for use with life sup- port and other designated “critical” devices. This section describes the NX’s environmental requirements and mechanical considerations that must be taken into account when planning the positioning and cabling of the UPS equipment.
  • Page 11: Storing For Delayed Installation

    1.2.1 Storing for Delayed Installation If the equipment will not be installed immediately, it must be stored indoors where the humidity is no higher than 90% and the temperature is no higher than 104°F (40°C). The storage area must protect the NX from excessive moisture (see 6.2 - UPS Environmental).
  • Page 12: Special Considerations For 1+N Systems

    1.4.3 Special Considerations for 1+N Systems 1. Consider the grounding configuration of your system before finalizing module placement. For optimal ground performance, the NX modules should be close together. 2. For optimal load-sharing performance, the UPS output cables should be approximately the same length, plus or minus 20 percent.
  • Page 13: Clearances

    1.6.1 Clearances There are no ventilation grilles on the sides or rear of the UPS. The sides must be accessible during installation. After installation, the unit may be placed with the rear against a wall and optional cabi- nets on either side. To enable routine tightening of power terminations within the UPS, make sure there is sufficient clearance in front of the NX to permit free passage of personnel with the door fully opened.
  • Page 14: Optional Cabinets

    1.6.4 Optional Cabinets If your NX installation includes a Maintenance Bypass Cabinet, the NX must be positioned to allow the Maintenance Bypass Cabinet to be bolted to left side of the NX (see Figure 1). Cables from the Maintenance Bypass Cabinet must be brought through the bottom side of the NX for connection. The Maintenance Bypass Cabinet must be cabled and bolted to the NX before the UPS and bypass cabinet are moved into their final position.
  • Page 15: E Lectrical C Onnections

    LECTRICAL ONNECTIONS The UPS requires both power and control cabling once it has been mechanically installed. All control cables must run separate from power cables in metal conduits or metal ducts that are electrically bonded to the metalwork of the cabinets to which they are connected. WARNING Before connecting input power to the NX, ensure that you are aware of the location and operation of the overcurrent protection devices that connect the UPS input/bypass supply to...
  • Page 16: Ups Input Configuration

    2.1.2 UPS Input Configuration Figure 2 illustrates the NX in a split bypass (dual-input) configuration. In this configuration the Static Bypass and the Maintenance Bypass lines are supplied from a separate feed from the Main input. Both sources must be protected externally with properly sized protective devices. By default, the unit ships with internal links installed between the Bypass input and Main input (Single Input configuration).
  • Page 17: Cable Connections

    2.1.4 Cable Connections The rectifier input, bypass and output are easily accessible from the left side of the unit for installa- tion. All require lug type terminations. They are connected to busbars on the left side of the NX and below the switch, as shown in Figure 3.
  • Page 18: Safety Ground

    UPS Rectifier and Bypass Input Supply • Protection from excessive overcurrents and short circuits in power supply input External overcurrent protection for the AC output circuit is to be provided. See 6.4 - UPS Elec- trical Characteristics and Table 12 for overload capacity.
  • Page 19: Cabling Procedure

    2.1.7 Cabling Procedure CAUTION The operations described in this section must be performed by authorized electricians or qualified technical personnel. If you have any difficulties, contact your local Liebert representative or Liebert Global Services. NOTE Hydraulic pressure pliers, combinative tools and piston ring pliers should be used to connect AC wiring.
  • Page 20: Internal Ups Battery Connections

    Internal UPS Battery Connections The UPS internal batteries will be connected at the factory, EXCEPT the Anderson connections between the shelves and to the fuses. WARNING The DC bus is live when this internal battery connection is made. This connection is to be performed ONLY by Liebert Global Services at startup.
  • Page 21: Dry Contacts

    Figure 7 Auxiliary terminal block detail (Monitoring Board) J13 J21 J25 BFP INV ACF Dry Contacts The UPS provides input dry contacts and output dry contacts. 2.3.1 Input Dry Contacts There are several input dry contacts at the X3 slot. Figure 8 Input dry contacts Table 1...
  • Page 22: Maintenance Bypass Cabinet Interface

    2.3.2 Maintenance Bypass Cabinet Interface J26 and J30 are the MBC interface. Table 2 Maintenance bypass cabinet interface Position Name Description J26.1 T_IT Input transformer over temperature (N.C.) J26.2 AUX_I Reserved J26.3 +12V +12V Power J26.4 Power Ground J30.1 FUSE Reserved J30.2 F_FAN...
  • Page 23: Output Dry Contacts

    NOTE The Emergency Stop action within the UPS shuts down the rectifier, inverter and static bypass. It does not internally disconnect the input power supply. To disconnect ALL power to the UPS, open the upstream feeder breaker(s) when the remote EPO is activated.
  • Page 24: Figure 11 Epo Wiring For Firmware M200 Or Later

    The Emergency Stop action within the UPS shuts down the rectifier, inverter and static bypass. It does not internally disconnect the input power supply. To disconnect ALL power to the UPS, open the upstream feeder breaker(s) when the remote EPO is activated.
  • Page 25: B Attery I Nstallation

    ATTERY NSTALLATION Introduction Liebert recommends that the batteries in external cabinets match the internal batteries in the NX in manufacturer and type. If using multiple sets of batteries connected in parallel to provide the required battery backup run times, fit each set with an isolating device to permit working on one of the battery sets while leaving the others in service and providing backup protection.
  • Page 26: External Battery Cabinet Installation

    External Battery Cabinet Installation 3.4.1 Matching Battery Cabinets Two sizes of optional battery cabinets are available. Refer to Figures 13 and 14. The same model bat- tery cabinet may be installed in parallel in multiple cabinet strings for additional capacity. Battery run time depends on the cabinet model, the number of cabinets and the load on the UPS.
  • Page 27: Figure 13 Narrow Battery Cabinet, 27 In. (690Mm) - Rear View

    Figure 13 Narrow battery cabinet, 27 in. (690mm) - rear view cable entry Battery trays Figure 14 Wide battery cabinet, 57 in. (1488mm) - front view Battery tray support Battery tray Top cable entry Battery Installation BCB plate and BCB Batteries BCB plate and Service...
  • Page 28: Installation Considerations

    Battery Installation 3.4.3 Installation Considerations Position—Liebert battery cabinets come in versions specific to either the left or right side of the UPS. Control wires and power cables are cut to different lengths for the different versions. If the sys- tem includes a matching maintenance bypass cabinet (MBC), the MBC should be mounted to the left of the UPS (nearest the busbars) and the battery cabinet(s) should be installed to the right of the UPS.
  • Page 29: Figure 15 Internal Cable Wiring From Battery Cabinet To Liebert Nx

    Figure 15 Internal cable wiring from battery cabinet to Liebert NX Power cables from output power switch Power cables from batteries Power cables (black) enter channel down side of NX to power input connections Figure 16 Battery tray and supports ...
  • Page 30: Connecting The Battery Cabinet To The Ups

    3.4.4 Connecting the Battery Cabinet to the UPS After the battery cabinet equipment has been positioned and secured for operation and the batteries have been connected, connect the power cables as described below. (See Figure 34.) 1. Verify that all incoming high and low voltage power circuits are de-energized and locked out or tagged out before installing cables or making any electrical connections.
  • Page 31: Maintenance Bypass Cabinet

    AINTENANCE YPASS The Maintenance Bypass Cabinet is designed to operate in UPS mode, bypass mode and maintenance mode. The mode is selected using the Bypass Switch. Figure 17 Single UPS with external Maintenance Bypass Cabinet—typical configuration Input Mains Supply A B C UPS 1 Fuse Battery 1...
  • Page 32: Bypass Mode

    Bypass Mode When the Maintenance Bypass Cabinet is in the Bypass mode, it provides an alternate path for power to the connected equipment. Should the UPS need to be taken out of service for limited maintenance or repair, manual activation of the bypass will cause an immediate transfer of the equipment from the UPS inverter to the bypass source.
  • Page 33: Power Cable Installation

    4.6.2 Power Cable Installation Refer to Tables 29, 30 and 32 when selecting cables. NOTE Transient and steady state earth leakage currents may occur when starting the equipment. This should be taken into account when selecting ground current detection devices because these will carry the earth leakage currents of both the UPS equipment and the load.
  • Page 34: Figure 20 Maintenance Bypass Control Wire Location

    7. Connect the system input cables between the Maintenance Bypass Cabinet 'UPS Input' Busbars (A-B-C N terminals) and UPS input busbars (A-B-C N terminals) and tighten the connections to 44 lb-in. (5 N-m) (M6 bolt). 8. Connect the system outnput cables between the Maintenance Bypass Cabinet 'UPS Output' Busbars (A-B-C N terminals) and UPS output busbars (A-B-C N terminals) and tighten the connections to 44 lb-in.
  • Page 35: Bolting Cabinets Together

    Bolting Cabinets Together NOTE UPS wiring must be completed before the cabinets are bolted together. 1. Line up cabinets so that mounting holes are aligned. 2. Using supplied hardware, bolt the cabinets together. The bolts may be inserted from either the UPS side or from the MBS side, whichever is more convenient.
  • Page 36: Options

    PTIONS Load Bus Synchronization The Load Bus Synchronizer (LBS) keeps the output of two independent UPS systems or parallel UPS systems in synchronization even when the systems are operating in different modes and even when either or both systems are operating on batteries. When the LBS is used, one UPS system is desig- nated as master, the other as slave.
  • Page 37: Configuring Parallel System Operation

    The 1+N system is used to: • Increase the reliability of the system to ensure adequate power supply to the critical load con- nected. • Increase serviceability and allow the execution of maintenance operations and reparations with- out affecting the ordinary operating conditions of the system (depending on the redundancy level).
  • Page 38: Operating Principles

    The sequence to transfer to maintenance bypass mode is the same as for transferring a single- module system. The maintenance bypass switches should be switched on as synchronously as pos- sible. Thus the system can be repaired without interrupting the power supply to critical load. Installing Parallel System The basic installation procedure of parallel system is the same as that of single module system.
  • Page 39: Power Cables

    5.3.5 Power Cables Wiring of power cables is similar to that of single module system (See 2.1 - Power Cabling). The bypass sources of all modules should be the same, and the outputs should be connected altogether cor- rectly. Power cables will be supplied by customer. Power cables to the UPS’s of the 1+N paralleling cabinet must be routed through either the top or bottom entry access of the UPS.
  • Page 40: Figure 24 Auxiliary Dry Contact Cables For Output Breaker In Multi-Module System

    Figure 24 Auxiliary dry contact cables for output breaker in multi-module system CAUTION The auxiliary control wire must be installed to ensure proper operation of the system. NOTE For startup procedure, see the UPS operations and maintenance manual, SL-25210. Figure 25 Dry contacts, multiple UPS modules with distribution panel UPS 1 M3 Board Ext.
  • Page 41: Emergency Power Off (Epo)

    5.3.7 Emergency Power Off (EPO) The external emergency stop facility is identical to that described for the single unit installation— that an individual emergency stop button is provided for each unit. Figure 26 Connecting EPO push button Normally Open EPO Normally Closed EPO UPS2...
  • Page 42: Battery Circuit Breaker Box

    Battery Circuit Breaker Box The box contains the same battery isolating circuit breaker as mounted in the battery cabinet. Two battery circuit breaker boxes are available for use in installations where the battery is not installed in the battery cabinet, in which case the appropriate battery box is fitted as close as possible to the battery and connected to the UPS equipment as illustrated in Figure 27.
  • Page 43: Figure 27 Battery Circuit Breaker Box Connections

    Figure 27 Battery circuit breaker box connections 10.8" 3.9" (274mm) (98mm) 5.4" (137mm) (3) 1/2" (12.7mm) dia. knockouts for control wiring conduit entry Top View 20.0" (508mm) 2.5" 15.0" (63.5mm) (381mm) 32.3" (819.2mm) Front View .31" dia. (Typ. 4 places) Bottom View NOTES: 1.
  • Page 44: Ups Specifications

    UPS S PECIFICATIONS These specifications describe requirements for the Liebert NX UPS. Conformity and Standards The UPS has been designed to conform to the following standards: • IEEC1000-4-5 • ASME • CSA 22.2, No. 107.1 • FCC Part 15, Class A •...
  • Page 45: Ups Electrical Characteristics

    UPS Electrical Characteristics Table 10 UPS terminal Input (for single-input unit) Nominal Maximum Unit Input Input Rating Current Current Rectifier input (for dual input unit only) Nominal Maximum Unit Input Input Rating Current Current Bypass input (for dual input units) Nominal Unit Input...
  • Page 46: Battery Manufacturers And Models

    6.4.1 Battery Manufacturers and Models Either of two manufacturers’ batteries will be installed in the NX 10-30 kVA 208V as shipped. Below are the battery makers and the models they supply. Table 11 Approved batteries Battery Manufacturer Enersys Yuasa C&D Dynasty UPS12-100MR 6.4.2 Input Rectifier...
  • Page 47: Inverter Output

    6.4.4 Inverter Output Table 14 Inverter output Rated Power Rated voltage, VAC Supply Frequency, Hz Rated Power, kW Three -phase transient overload, min. load Voltage Regulation % Frequency Regulation % Maximum rate of change of frequency, Hz/sec Current rating of neutral cable, A 6.4.5 Bypass Input Table 15...
  • Page 48: Installation Drawings

    NSTALLATION RAWINGS The diagrams in this section illustrate the key mechanical and electrical characteristics of the NX UPS System cabinets. Figure 28 Dimensional view- front and left side views 1600 FRONT VIEW 1. All dimensions are in millimeters. 2. A minimum of 24 inches clearance above the unit is required for air exhaust. 3.
  • Page 49: Figure 29 Dimensions Continued-Top And Bottom Views

    Figure 29 Dimensions continued—top and bottom views TOP VIEW Figure 30 Main components—typical unit Monitor Board (U2) IntelliSlot Communication Ports Input Breaker Rotary System Switch Input Breaker Access Plate Internal and External Battery Terminal Block Access Plate Rear stabiliz- ing foot Air Exhaust Power Cable Entry Area...
  • Page 50: Figure 31 Cable Connections

    Figure 31 Cable connections NOTES 1. All dimensions are millimeters. 2. Top and bottom cable entry available through removable access plates. Remove, punch to accommodate conduit size and replace. 3. Control wiring and power wiring must be run in separate conduit. Output and input cables must be run in separate conduit.
  • Page 51: Figure 32 Location Of Internal Batteries

    Installation Drawings Figure 32 Location of internal batteries Battery 186mm 417mm 687mm...
  • Page 52: Figure 33 Battery Connections

    Figure 33 Battery connections TOP LAYER W501 3pcs W500 18pcs W510 to W511 W511 to W510 W507 to W506 DYNASTY BATTERY W502 to W503 W503 to W502 W509 to W508 CON4 W505 to W504 Installation Drawings MIDDLE LAYER W504 to W505 BOTTOM LAYER W508 to W509...
  • Page 53: Figure 34 Battery Cabinet Interconnection

    Figure 34 Battery cabinet interconnection Refer to Table 16 for key to interconnection Connection Detail UPS Module Front View with doors removed NOTES: 1. All Liebert-supplied cable must be repositioned prior to and while the cabinets are being placed in their final installed location.
  • Page 54: Figure 35 Maintenance Bypass Interconnection

    Figure 35 Maintenance Bypass interconnection Refer to Table 17 for key to interconnection Maintenance Bypass/Transformer Cabinet front view without front door and panel NOTES 1. All Liebert-supplied cable must be repositioned prior to and while the cabinets are being placed in their final installed location.
  • Page 55: Figure 36 Nx 1+1 Parallel Cabinet Interconnections

    Figure 36 NX 1+1 parallel cabinet interconnections E1,E2 F1,F2 F1, F2 K1,K2 D1,D2 UPS Module Left Side View (Without Side Panel) NOTES: 1. All Liebert-supplied cable will need to be repositioned prior to and while setting the cabinets in their installed location.
  • Page 56: Figure 37 Lineup Detail-Slimline Distribution Cabinet To Nx

    Figure 37 Lineup detail—SlimLine distribution cabinet to NX NOTES: 1. All Liebert-supplied cable will need to be repositioned prior to and while setting the cabinets in their installed location. 2. All interconnection cables and hardware supplied by Liebert. 3. AC connections must be made to the UPS module before attaching. 4.
  • Page 57: Figure 38 Lineup Detail-1+N Type A Connection To Nx

    Figure 38 Lineup detail—1+N Type A connection to NX 1. All Liebert-supplied cable must be repositioned prior to and while setting the cabinets in their installed location. 2. All interconnection cables and hardware supplied by others. 3. AC connections must be made to the UPS modules before attaching paralleling cabinet to UPS modules 4.
  • Page 58: Figure 39 Lineup Detail-1+N Type A1 Connection To Nx

    Figure 39 Lineup detail—1+N Type A1 connection to NX 1 + N Parallel Cabinet (front view without front door and panel) UPS Module Left Side View (without side panel) Table 21 Interconnect wiring—1+N Type A1 connection to NX From Utility AC Source Utility AC Source Utility AC Source D1-D4...
  • Page 59: Figure 40 Lineup Detail-1+N Type B Connection To Nx

    Figure 40 Lineup detail—1+N Type B connection to NX I1, I2 1 + N Parallel Cabinet (front view without front door and panel) UPS Module Left Side View (without side panel) Table 22 Interconnect wiring—1+N Type B connection to NX From A1-A4 Utility AC Source...
  • Page 60: Figure 41 Lineup Detail-1+N Type B1 Connection To Nx

    Figure 41 Lineup detail—1+N Type B1 connection to NX 1 + N Cabinet Side View (without side panel or door) (front view without front door and panel) UPS Module Left Side View (without side panel) Table 23 Interconnect wiring—1+N Type B1 connection to NX From Utility AC Source Utility AC Source...
  • Page 61: Figure 42 Lineup Detail-1+N Type C Connection To Nx

    Figure 42 Lineup detail—1+N Type C connection to NX 1 + N Cabinet Side View (without side panel or door) (front view without front door and panel) UPS Module Left Side View (without side panel) Table 24 Interconnect wiring—1+N Type C connection to NX From Utility AC Source Utility AC Source...
  • Page 62: Figure 43 Lineup Detail-1+N Type C1 Connection To Nx

    Figure 43 Lineup detail—1+N Type C1 connection to NX 1 + N Cabinet Side View (without side panel or door) (front view without front door and panel) 1. All Liebert-supplied cable must be repositioned prior to and while setting 2. All interconnection cables and hardware supplied by others. 3.
  • Page 63: Figure 44 Lineup Detail-1+N Type D Connection To Nx

    Figure 44 Lineup detail—1+N Type D connection to NX 1 + N Cabinet Side View (front view without front door and panel) (without side panel or door) UPS Module Left Side View (without side panel) Table 26 Interconnect wiring—1+N Type D connection to NX From Utility AC Source Utility AC Source...
  • Page 64: Figure 45 Slimline Locations

    Figure 45 SlimLine locations 1 + N Paralleling Cabinet Installation Drawings Battery Battery 1 + N Paralleling Cabinet...
  • Page 65: Specifications And Technical Data

    PECIFICATIONS AND Lug Size and Torque Requirements Use commercially available solderless lugs for the wire size required for your application. Refer to Table 27. Connect wire to the lug using tools and procedures specified by the lug manufacturer. Table 27 Torque specifications Nut and Bolt CombinationS Bolt Shaft Size...
  • Page 66: Table 29 Maintenance Bypass Cabinet Electrical Data (Single Input)

    Table 29 Maintenance bypass cabinet electrical data (single input) Maintenance Bypass Bypass Cabinet I/P Voltage Max Input kVA Type (VAC) Current A, J B, K B, K B, K C, L C, L C, L D, M D, M D, M D, M D, M E, N...
  • Page 67: Table 30 Maintenance Bypass Cabinet Electrical Data (Dual Input)

    Table 29 Maintenance bypass cabinet electrical data (single input) (continued) Maintenance Bypass Bypass Cabinet I/P Voltage Max Input kVA Type (VAC) Current D, M E, N E, N E, N A, J B, K B, K B, K C, L C, L C, L D, M...
  • Page 68: Table 31 Multi-Module Bypass Cabinet Electrical Data

    Table 30 Maintenance bypass cabinet electrical data (dual input) System Rectifier I/P Voltage Max Input kVA Type (VAC) Current F, P F, P F, P F, P F, P F, P F, P F, P F, P F, P Table 31 Multi-module bypass cabinet electrical data System System...
  • Page 69 Table 31 Multi-module bypass cabinet electrical data (continued) System System I/P Voltage Size Type (VAC) A00, BR0 CR1, DR1 CR1, DR1 CR1, DR1 CR1, DR1 CR1, DR1 CR1, DR1 CR1, DR1 CR1, DR1 CR1, DR1 CR1, DR1 CR1, DR1 CR1, DR1 SR0, W00 System System...
  • Page 70 Table 31 Multi-module bypass cabinet electrical data (continued) System System I/P Voltage Size Type (VAC) E00, FR0 G01, GR1 TR0, X00 System System Max Input Input OCP O/P Voltage Current CB Size (A) (VAC) Specifications and Technical Data Nominal O/P Output OCP Current Rating (A) CB Size (A)
  • Page 71 Table 31 Multi-module bypass cabinet electrical data (continued) System System I/P Voltage Size Type (VAC) E00, FR0 G01, GR1 TR0, X00 System System Max Input Input OCP O/P Voltage Current CB Size (A) (VAC) Specifications and Technical Data Nominal O/P Output OCP Current Rating (A) CB Size (A)
  • Page 72 Table 31 Multi-module bypass cabinet electrical data (continued) System System I/P Voltage Size Type (VAC) J00, KR0 UR0, Y00 System System Max Input Input OCP O/P Voltage Current CB Size (A) (VAC) Specifications and Technical Data Nominal O/P Output OCP Current Rating (A) CB Size (A)
  • Page 73 Table 31 Multi-module bypass cabinet electrical data (continued) System System I/P Voltage Size Type (VAC) J00, KR0 UR0, Y00 System System Max Input Input OCP O/P Voltage Current CB Size (A) (VAC) Specifications and Technical Data Nominal O/P Output OCP Current Rating (A) CB Size (A)
  • Page 74: Table 32 Maintenance Bypass Cabinet Lug Sizes

    Table 32 Maintenance bypass cabinet lug sizes Input Unit Nominal System Rating Input Voltage Bolt Size 6M (1/4”) 6M (1/4”) 6M (1/4”) 6M (1/4”) 6M (1/4”) 6M (1/4”) 6M (1/4”) 6M (1/4”) 6M (1/4”) 6M (1/4”) 6M (1/4”) 6M (1/4”) 6M (1/4”) 6M (1/4”) 6M (1/4”)
  • Page 75: Table 33 Maintenance Bypass Cabinet Weights

    Table 32 Maintenance bypass cabinet lug sizes (continued) Output Unit Nominal System Rating Output Voltage Bolt Size 6M (1/4”) 6M (1/4”) 6M (1/4”) 6M (1/4”) 6M (1/4”) 6M (1/4”) 6M (1/4”) 6M (1/4”) 6M (1/4”) 6M (1/4”) 6M (1/4”) 6M (1/4”) 6M (1/4”) 6M (1/4”) 6M (1/4”)
  • Page 76: Cable Lengths: Floor To Connection Point Inside Ups

    Table 35 Maintenance bypass cabinet dimensions Unit Width Depth inch 27.2 31.4 Table 36 Multi-module paralleling cabinet dimensions 1+1 Cabinet Type 1+N Narrow Types A00, BR0, CR1, DR1 1+N Cabinet Type 1+N Narrow Types A00, E00, J00 1+N Wide All other types Cable Lengths: Floor to Connection Point Inside UPS To help calculate the total cable length required, refer to Table 37 for the distance from the floor to selected connection points inside the NX.
  • Page 77 Specifications and Technical Data NOTES...
  • Page 78 Specifications and Technical Data...
  • Page 80 Embedded Computing Connectivity Embedded Power DC Power Monitoring Business-Critical Continuity, Emerson Network Power and the Emerson Network Power logo are trademarks and service marks of Emerson Electric Co. ©2006 Emerson Electric Co. Technical Support / Service monitoring@emersonnetworkpower.com Outside the US: 614-841-6755 upstech@emersonnetworkpower.com...

Table of Contents

Save PDF