4. Disconnect shore power. Take away the shore power by turning the shore power breaker off, or
unplugging the shore power. The inverter should transfer to inverter mode immediately. This will
be indicated by a clicking sound as the internal transfer relays change position. The inverter will
begin to "buzz" as it takes power from the batteries and uses it to power the loads. The loads
should continue to operate uninterrupted.
The above steps will complete a functional test of the inverter. If all areas pass, the inverter is ready
for use. If any area fails, figure out why before proceeding. The troubleshooting guide in Appendix
A: Troubleshooting will help you solve problems you encounter. If any of the inverter's internal
setpoints are to be adjusted, consult the booklet included with the RC7 remote control.