Adjustment history Version Date Description 04/06/2018 Original version www.betafence.com...
Page 3
If this is the case, please ensure that the cable is long enough to reach the junction boxes in the posts. The concrete must have hardened completely before installing the gate. www.betafence.com...
Page 4
Hold the drilling templates and drill the holes. Normally 300 mm deep in the concrete with 100 mm above the surface. This could be different when the foundations are not the same height and one post needs to be placed higher up. www.betafence.com...
Page 5
1. Attach the anchors with special glue and check that the template fits over them (otherwise the base plate of the post will not fit). 2. Allow the glue to dry well before placing the post. 3. Adjust the nuts and washers, paying attention to the required height of the post, taking into account ground clearance (adjust using a spirit level).