  • Page 1 SPH 3000-6000TL-HUB Series User Manual...
  • Page 2 SPH series products manufactured by Shenzhen Growatt New Energy Technology Co., Ltd. (hereinafter referred to as Growatt). Please read this manual carefully and keep it in a place that is convenient for installation, operation and access. Growatt reserves the right to make any modifications to this manual without further notification to customers.
  • Page 3 Contents 1 Product Introduction ..............1 1.1 Intended Use ......................1 1.2 System Diagram....................2 1.2.1 SPH 3000-6000TL-HUB ..................2 1.2.2 ALP 5.0L-E1 ....................... 4 2 Safety ..................2.1 General Safety...................... 6 2.2 Safety Precautions ....................6 2.2.1 Environment Requirements ................6 2.2.2 Safe Operation and Protection Measures ............
  • Page 4 4.4.10 PE Cable Wiring Instructions................ 46 4.4.11 System Wiring Instructions ................47 4.5 Install the decorative cover ................53 5 Power on/off the System ............55 5.1 Power on the System ..................55 5.2 Power off the System ..................55 5.3 Power on/off the battery system separately ..........
  • Page 5 1 Product Overview 1.1 Intended Use The SPH grid-connected system consists of PV modules, SPH 3000-6000TL-HUB inverter, ALP series batteries, public grid and others, as shown in Figure 1. It comes with two independent MPPTs. Up to 8 batteries can be connected in parallel.
  • Page 6 1.2 System Diagram PV Input Grid EPS LOAD Figure 1.1 System diagram of the SPH 1.2.1 SPH 3000-6000TL-HUB The SPH 3000-6000TL-HUB inverter is mainly composed of inverter circuit, buck-boost converter circuit, control circuit and communication circuit. The product appearance is shown below: A: Dimensions of SPH 3000-6000TL-HUB Dimensions(unit:mm) Figure 1.2 Appearance of the SPH...
  • Page 7 A (mm) B (mm) C (mm) Weight(kg) SPH 3-6KTL-HUB B: External terminals of SPH 1234 111213 Figure 1.3 Wiring terminals of SPH Common ground point for the battery and the SPH Ground point inverter CAN Port Connected to the battery CAN communication port BAT- terminal Connected to the negative battery terminal BAT+ terminal...
  • Page 8 C: Button description Symbol Designation Description Operate the display screen and set system Push button parameters Steady green SPH runs normally Steady red Fault state SPH status indicator Blinking green Alarm state Blinking red 2. Software updating 1.2.2 ALP 5.0L-E1 The ALP 5.0L-E1 consists of a battery module (including battery cells and mechanical components), a battery management system (BMS), and the power supply and communication terminals.
  • Page 9 B: External terminals of ALP 5.0L-E1 PCS CAN communication port LINK-IN CAN communication port Negative battery terminal Positive battery terminal USB port DC Breaker Battery power button LINK-OUT CAN communication port Battery ground point Figure 1.5 Wiring terminals of ALP 5.0L-E1 C: Battery indicator description Figure 1.6 ALP 5.0L-E1 LED indicators Name...
  • Page 10 Before installing or using the equipment, please read the instructions carefully and observe the all safety precautions at all time. Growatt shall not be liable for any consequence of the following circumstances: Damage during the transportation by the customer.
  • Page 11 Ÿ Do not dispose the batteries in a fire, which may cause an explosion. Do not put the battery in contact with liquids. Ÿ For indoor installation, do not install the equipment in the bedroom, living Ÿ room, kitchen, etc. For outdoor installation, please build a sun and rain shelter to protect the Ÿ...
  • Page 12 2.3 Label Description Label Description Risk of high voltages which might lead to electric shocks Burn hazard. Hot surface. Do not touch. Delayed discharge: Residual voltage exists after the SPH is powered off. Wait at least 5 minutes until it discharges to the safe level Grounding: indicates the position for connecting the PE cable...
  • Page 13 Description Label Ensure the correct polarity Keep away from open flames and heat source Refer to the manual Do not dispose of the product together with the household waste but in accordance with the disposal regulations for electronic waste applicable at the installation site Regulatory Compliance Mark (RCM) for Australia Indicates a potentially hazardous situation, if not avoided, could result in serious injury or death...
  • Page 14 CAUTION The SPH inverter emits radiate, which might affect your health aversely! Do not stay close to the SPH inverter (within 20 cm) for a long time. Grounding the SPH inverter Information Please ensure that SPH inverter has been securely connected to ensure personal safety.
  • Page 15 WARNING Figure2. 3 Battery usage safety warnings Figure 2. 4 Inverter label Be sure that the operating ambient temperature is between 0 and 50°C, otherwise the battery will stop working. WARNING...
  • Page 16 If the battery system is soaked or submerged in water, do not Flood touch the batteries to avoid electric shock. Contact Growatt or emergency your distributor immediately for technical assistance. The shell damage requires extra attention as it is of high risk. Do...
  • Page 17 7) If the battery module has not been used for more than 6 months, it needs to be recharged. In this case, a recharge device is required. For details, please contact Growatt customer service. 8) Avoid exposure to intense infrared radiation.
  • Page 18 Installation and Cable Connections 4 Read through this manual before installation to get familiar with Ø the product information and safety precautions. Ø Only qualified and well-trained technicians who fully understand the whole photovoltaic system, grid network, battery system, working principle and national/local standards are allowed to perform operations on the SPH system.
  • Page 19 E. Observe the clearance requirements: 1) Keep the SPH at least 600 mm away from any heat source such as the water heater, gas heater, air conditioner or any other equipment. 2) Keep a distance of at least 600 mm from the outlet. 3) Keep a distance of at least 600 mm from a window or other vent.
  • Page 20 Marker Level Figure 4. 2Installation tools Please wear the following safety gears: Safety Goggles Safety Shoes Insulated Gloves Figure 4. 3 Safety gears 4.3 Installation Procedure 4.3.1 Checking before Installation Check the package before unpacking it. If any damage is found, do not unpack Ø...
  • Page 21 2. Cables in Figure E are not standard accessories. They are required only when installing 5 (or above) battery modules in parallel. In case that you need to purchase the parallel cables, please contact Growatt after-sales services. 3. “N” stands for the number of the battery module.
  • Page 22 SPH TL-HUB*1 ShineWiFi*1 AC Grid connector*1 EPS connector*1 Mc4 connector*2 Dry contact connector*1 CT*1 Upper left decorative cover*1 Lower left decorative cover*1 Die cast bracket*1 Quick installation Manual *1 User Manual *1 Warranty card *1 Certificate of conformity *1 Die cast bracket*1 Small junction box decorative cover*1 Anti-tip connecting piece*2 M6 expansion screw*2...
  • Page 23 right trim cover*1 left trim cover*1 Figure 4. 6 Packing list of the battery module of the SPH system For an SPH system, only one SPH inverter is required, and 1-8 battery modules can be configured. NOTICE 4.3.2 Floor-mounted Installation NOTE: 1.
  • Page 24 Unit: mm Wall ≥300mm ≥300mm Ground Ground ≥300mm ≥300mm Ground Figure 4. 7 Installation angle and clearances for floor-mounted installation Step 2: Position the first BM onto the base and mark the hole positions for fixing the first BM using a marker. Install anti tipping plates on the sides of the battery using M4 screws.
  • Page 25 Step 3: Mark all hole positions with the paper drilling template and drill holes. Unit: mm Recommended height:115mm Figure 4.9 Dimensions of the drilling template Dia 8.0mm M6 expansion bolt Deep45~50mm 90° Remove the battery,mark the hole positions to install the batteries. Install the M6 expansion bolt and tighten the nut.
  • Page 26 Step 4: Install and secure the BMs in turn. Secure the connecting pieces on the both sides of the battery moudle using the M4 screws,and tighten the 6 screws. Install the connecting pieces on both sides and tighten the 2 screws. Install the anti-tipping plates on bothsides to fix the modules to the wall.
  • Page 27 Step 6: Secure the inverter and install the decorative cover. Fix the anti tipping component to the inverter and wall using M4 screws and expansion screws respectively. Install the connecting piece between inverter and battery using M4 screws. Fix the inverter die-casting bracket to the battery using M4 screws. Install the inverter front panel and secure it with M4 screws.
  • Page 28 Unit: mm -3°≤δ≤3° δ≤3° ≥900mm Wall ≥300mm ≥300mm Ground Ground Figure 4. 14 Installation angle and clearances for wall-mounted installation Step 2: Assemble the wall mount bracket Figure 4. 15 Assemble the wall mount bracket...
  • Page 29 Step 3: Confirm the mounting position of the wall mount bracket, mark the hole positions and drill holes. Level Dia 8.0mm 90° Deep45~50mm Marker Ensure that the mounting position is level using a level. Mark the hole positions using a marker Drill holes as illustrated in the figure.
  • Page 30 Step 5: Mark all hole positions with the paper drilling template and drill holes. Dia 8.0mm M6 expansion bolt Deep 45~50mm Install the M6 expansion bolt and tighten the nut. Remove the battery,mark the hole positions to install the batteries. Figure 4.
  • Page 31 Step 6: Install and secure the BMs in turn. Secure the connecting pieces on the both sides of the battery moudle using the M4 screws,and tighten the 6 screws. Install the connecting pieces on both sides and tighten the 2 screws. Install the anti-tipping plates on bothsides to fix the modules to the wall.
  • Page 32 Step 8: Secure the inverter and install the decorative cover. Fix the anti tipping component to the inverter and wall using M4 screws and expansion screws respectively. Install the connecting piece between inverter and battery using M4 screws. Fix the inverter die-casting bracket to the battery using M4 screws. Install the inverter front panel and secure it with M4 screws.
  • Page 33 Note: Figure A illustrates the installation of the communication terminal; Figure B illustrates the removal of the communication terminal. 4.4 .2 Power Terminal Wiring between BMs/between BM and SPH Battery/SPH side Battery/SPH side Wire side Wire side Press Figure 4. 24 Power terminal wiring between BMs/between BM and SPH Note: 1.
  • Page 34 Step 1: Loosen the screws on both sides of the anti-tamper cover. Step 2: Remove the anti-tamper cover. Step 3: Rotate the EPS connector to remove it from the inverter and pull it out. 4.4 .3.2 Install the EPS Connector The Inverter Side Tightening the EPS connector...
  • Page 35 Positive metal contact Positive connector 8-10 mm Negative connector 8-10 mm Ensure that the cable cannot be Give the wire and crimp a slight Negative metal contact pulled out after being crimped. tug to make sure they are secure. Tighten the locking nut.
  • Page 36 SPH, the error message PV ISO Low is displayed. The grounding of photovoltaic modules and photovoltaic Ø generators must meet local grounding requirements. GROWATT recommends connecting the generator frame and other conductive surfaces to ensure continuous conduction to the ground for optimal protection of systems and personnel.
  • Page 37 4.4 .4 Grid Connector Wiring Instruction 4.4 .4.1 Install the Grid Connector Take the following parts from the accessory bag: Connection terminal Locking nut Sealing ring & threaded sleeve Figure 4. 27 Grid connector The Inverter Side Lock the housing Figure 4.
  • Page 38 4.4 .4.2 Remove the Grid Connector The Inverter The Inverter Side Side Removing the AC connector Figure 4. 29 Remove the Grid connector Step 1: Press the buckle out of the slot using a small screwdriver. Step 2: Unplug the AC grid connector. 4.4 .5 AC-side Cable Specification Recommendation Max cable length Conductor...
  • Page 39 Connect the PV input cables with the MC4 PV connectors. The procedure is as follows: 1. Turn off the PV switch. 2. Insert the positive and negative cables of the PV panel into the MC4 connectors, then connect the positive (+) of the connecting cable to the positive (+) of the PV input connector, and connect the negative (-) of the connecting cable to the negative (-) of the PV input connector, noting that the PV input voltage and current should be within the permitted range:...
  • Page 40 4.4 .8 System Wiring 4.4 .8.1 System Wiring Battery side/ Battery side/ Wire side Wire side SPH inverter SPH inverter Figure 4. 34 Single-column system wiring diagram...
  • Page 41 Note: 1. The battery is not allowed to be installed while it is running. Before installation, the battery module circuit breaker should be disconnected and all indicator lights should be off. 2. Connect the battery power cables: Take out the positive and negative power cables from the accessory bag delivered with the battery package.
  • Page 42 4.4 .8.2 Dual-column system wiring diagram Cable raceway Cable raceway Bottom cable routing Rear cable routing Figure 4. 35 Dual-column system wiring diagram Note: 1. When installing the battery system in two columns, you can choose bottom cable routing by threading cables through the battery base the and cable raceway or the rear cable routing by installing a cable raceway on the wall directly as indicated in the figure above.
  • Page 43 4.4 .9 External Communication Port Installation 4.4 .9.1 External communication port description The SPH inverter has a total of 8 external communication ports. The appearance of the ports is shown in Figure 46. Each port contains 8 pins. Figure 4. 36 Communication ports PIN definition of the ports Silk DRMS...
  • Page 44 Silk 485-1/485-3 485-2 screen Definition Definition Definition Definition Definition Definition GND S Ntc- 485-1_ B 485-1_ B GND S Ntc- GND S GND S GND S Ntc- GND S Ntc- 485-1_ B 485-1_ B Ntc+ 485-1_ A 485-1_ A ntc+ ntc+ 485-3_ B 485-3_ B...
  • Page 45 4.4 .9.2 External Communication Terminal RJ45 connector Mounting Threaded RJ45 Seal ring Base sleeve termimal Communication cable Waterproof cover Anti-tamper Locking nut element Figure 4. 37 Communication terminal 4.4 .9.3 External Communication Terminal Installation Instructions Meter1/CT1 DRMS Inbuilt Meter1 485-1/485-3 -COM+ 485-2 Meter1/CT1...
  • Page 46 Unscrew the two swivel nuts from the waterproof cover by turning them counterclockwise. Remove the anti-tamper element. Loosen the screws on the snap handle. Turn the handle toward the inverter to remove the waterproof cover. Thread the external communication cable through the swivel nut, cable support sleeve and waterproof cover in turn.
  • Page 47 4.4 .9.4 External Communication Port Functions and Settings Instructions A. CAN Communication Port 1. If a lead-acid battery is used, you do not need to install this communication cable. 2. CAN battery communication and 485-2 battery communication cannot be installed simultaneously. Please choose the correct communication method according to the battery manual.
  • Page 48 CT working with the meter should be connected to the network port; only CTs provided by Growatt are supported. 2. Open the buckle of the CT, and you can see an arrow indicating the direction of the current flow.
  • Page 49 (4) In Australia, it is generally not recommended to use a CT for export limitation. If needed, please consult after-sales service. C. COM communication port 1. For unused cables such as the Dry Contact cable, do not remove the filler plug from the cable support sleeve.
  • Page 50 4.4.10 PE Cable Wiring Instructions The SPH must be reliably grounded with the PE cable. The ground point is shown below. The minimum wire gauge of the PE cable is 10 AWG. Figure 4. 42 PE cable wiring diagram PV array grounding The grounding conductor for the PV panel frame must be securely grounded on the PV array side, the inverter side, and the battery side.
  • Page 51 4.4.11 System Wiring Instructions The Growatt SPH 3000-6000TL-HUB is a single-phase inverter. Ø If the inverter is installed in Australia or New Zealand, it must NOT be used as part of a three-phase combination. Ø This inverter complies with IEC 62109-2 Clause 13.9 for ground fault alarm monitoring.
  • Page 52 Switch type Switch position Switch selection Grid-side circuit breaker/switch- disconnector, to be installed close to the inverter side; recommended to install one when the distance between the (depends on on- inverter and the main distribution panel site conditions) is greater than 3m or a blind spot exists between them;...
  • Page 53 4.4.11.2 Wiring Diagram B DC positive or grid fire DC negative or grid zero Grounding strap Distribution Box LOAD SW11 SW12 SPH3000- GRID 6000TL-HUB LOAD Main SW10 Meter GRID GRID Wiring diagrams for other European countries Figure 4. 45 Wiring diagram B Note: Diagram B is the wiring diagram for European countries.
  • Page 54 Switch type Switch position Switch selection Grid-side circuit breaker connected to the inverter, installed in the main distribution panel; follow local regulations to determine (mandatory) whether to install one; depends on the inverter capacity, recommended specification: ≤ 230VAC/35A. switch/breaker Grid input main circuit breaker, installed in Sw10 the main distribution panel;...
  • Page 55 4.4.11.3 Wiring Diagram C DC positive or grid fire DC negative or grid zero Grounding strap Distribution Box Manual LOAD Bypass switch SH3000- 600P0TL-HUB GRID GRID Australia Wiring Diagram Figure 4. 46 Wiring diagram C Note: Diagram C is an example of a grid-connected energy storage system wiring. There are no special requirements for the cable connections.
  • Page 56 Switch type Switch position Switch selection Grid-side circuit breaker, installed in the main distribution panel; depends on the SW6 (optional) inverter capacity, recommended specification: ≤ 230VAC/35A. AC breaker Off-grid output circuit breaker/switch- disconnector, installed in the main distribution panel; depend on the inverter (mandatory) capacity;...
  • Page 57 Please pay attention to the color of the connectors when Ø connecting power cables. Only connectors with the same color can be connected. For safe operation of the system, it is necessary to ensure Ø reliable grounding. This area is a restricted access area, which is explained as Ø...
  • Page 58 2. Install the decorative cover Insert the inverter-side stopper screw into the slot of the decorative cover. Tighten the screws to secure the inverter decorative cover using a screwdriver, and secure the battery decorative cover with screws after installing it. Figure 4.
  • Page 59 5 Power on and off the Battery System Ø Personnel who install and operate the SPH System must receive thorough training and possess the local national required qualifications before operation. Only qualified professionals and trained personnel are allowed to install, operate and maintain the equipment.
  • Page 60 5.3 Power on/off the battery system separately In case that the grid is not available, or when the battery needs to be connected to/disconnected from the system in operation, you might need to power on/off the battery system separately. 5.3.1 Power on the battery system Step 1: Ensure the battery system is properly connected to the inverter and turn on the battery circuit breaker.
  • Page 61 6 Commissioning and Maintenance 6.1 Preparation 6.1.1 Working Mode Description 6.1.1.1 Normal Mode Normal Mode indicates the normal operating state, including grid-connected mode and off-grid mode. Grid-connected Mode When the SPH operates in Grid-connected Mode, users can set appropriate working mode as needed. When configuring on the LCD screen with the buttons, you can only set the working mode for one time segment.
  • Page 62 Note: 1. To ensure maximum efficiency and long-term stable operation of the inverter, it is recommended not to exceed 80% of the maximum power rating at the EPS port. For example, for a 6 kW model, it is recommended to connect a maximum load of 4.8 kW, meaning all loads combined should not exceed 4.8 kW when operating.
  • Page 63 6.1.1.6 Shutdown Mode To shut down the SPH, all power sources must be disconnected, and the SPH inverter will automatically enter Shutdown Mode. The shutdown procedure is as follows: 1. Turn off the PV switch. 2. Turn off the battery-side breaker. 3.
  • Page 64 Position Description Displays the operating status Displays key information PV Input (If connected to two PV inputs, it will display two; otherwise, it will display one) SPH inverter Power flow line indicator Grid Battery (displayed with five girds, each representing 20%) Load output Wireless communication Rs232...
  • Page 65 For details, please refer to Section 1.2.1. 6.1.2.3 System Working Mode Settings Growatt products have been designed and tested according to the applicable international/regional standards. Upon receipt of the product, please set the corresponding safety regulations on the LCD screen based on your country/region.
  • Page 66 Work Mode Input &output para WorkMode Firmware version WorkMode FW Version:xxxx (Lead acid)Vb:xx.xV Battery (Lithium)Vb/Cb:xx.xV/xxx% information WorkMode Machine model WorkMode Model:xxxxxxxxxx Battery power Pbat: (+/-)XXXX W WorkMode Serial number WorkMode SerNo:xxxxxxxxxx PV1/PV 2 Ppv:xxxV/xxxV inpu power WorkMode System Time WorkMode PV1/PV2 Etu_a:xxxx.x KWh Vpv:xxxV/xxxV...
  • Page 67 Note: 1. Press "Down" to proceed (you can press "Up" to return to the previous page). 2. The working mode depends on the situation: If the SPH is in Normal Status, it will display "normal". If the SPH is in Standby Status, it will display "standby", and so on.
  • Page 68 A. Under Basic Parameter, press and hold OK for 1 second, then you can see the following settings options: Language: English, Italian, German System Time Lead-Acid Battery Charging Voltage: 58V (default) Discharge Low Voltage: 48V (default) Lead-Acid Constant Current: 25A (default) RS485 Address Italiano WorkMode...
  • Page 69 If energy quality and grid settings are selected during commissioning, these setting items should be locked and cannot be modified (unless otherwise authorized by Growatt) After completing energy quality and grid settings, verify compliance with safety regulations on the APP.
  • Page 70 F. Set PQRM Reset WorkMode P_ limit:Reset Volt-Watt:ON Limit_P :xx.x% PQRM:Volt-Var Default Default WorkMode Set PQRM Set OK ! Set OK ! SC : _ _ _ _ WorkMode WorkMode Reset P_ limit:Reset Enable Limit_P :xx.x% PQRM:Enable PQRM:Volt-Watt Default Disable Disable Set OK ! Set OK !
  • Page 71 C. Under DRY connect, press OK, then you can see the following options: WorkMode Dry Disable WorkMode WorkMode Generator:OK Dry Connect WorkMode Heater:OK Figure 6. 8 DRY connect settings D. Under COUNTRY/AREA, press OK, then you can set the country/area according to the safety regulations: Queensland Victoria...
  • Page 72 To modify the Country/Area, please follow the steps below: Press the “down”bitton WorkMode WorkNode Set Region Country/Area Press the “OK”botton Press the “OK”botton Region:A Press the “ESC”botton SC:____ Press the “OK”botton Press the “OK”botton WorkMode Ausralai Set OK! Press the “OK”botton Set OK! Figure 6.
  • Page 73 C. Under "Export Limit”, press "OK", then you can see the following settings options: You can adjust the Export Limitation parameter to control the power fed to the grid. If enabled, the power exported to the grid would be less than or equal to the pre-set value.
  • Page 74 C. Under "Mode Change”, press "OK", and you can see the following settings options: Sensor Type: Cable CT (default), Master, and Meter. Battery Type: Lithium battery or Lead-acid battery. Sensor:Cable CT Master Meter Workmode Mode Change Battery:Lithium Lead-acid Figure 6. 15 Mode Change settings J.
  • Page 75 Note: 1. "Power" is used to set the power of the battery. Since different batteries may have different power ratings, you need to check the maximum power of the battery. 2. Set the time format to 24 hours. If the end time is less than the start time, it defaults to spanning midnight.
  • Page 76 L. To facilitate installation and diagnose any faults that may cause operational issues during installation, a one-click installation diagnostics function is added: Before starting, please turn off the PV switch. During the installation diagnostics process, if customers have loads connected, please keep the loads running stable to ensure accurate testing.
  • Page 77 For details, refer to the datalogger's manual. Note: 1. You need to use Growatt ShineServer/ShinePhone for data monitoring. 2. After connecting the datalogger, upon initial battery power-on, no monitoring data would be available in the first 20 minutes as the SPH is establishing...
  • Page 78 Specifications 7 7.1 ALP 5.0L-E1 Specifications Parallel number Model ALP 5.0L-E1 ALP 10.0L-E1 ALP 15.0L-E1 ALP 20.0L-E1 Nominal Energy (kWh) Rated Energy (kWh) 13.8 18.4 Nominal Capacity (Ah) Rated Capacity (Ah) Nominal Voltage (V) 51.2 Voltage Range (V) 46.4~57.6 Rated Current (A) Max Current (A) Operating temperature 0℃~50℃...
  • Page 79 Parallel number Model ALP 25.0L-E1 ALP 30.0L-E1 ALP 35.0L-E1 ALP 40.0L-E1 Nominal Energy (kWh) Rated Energy (kWh) 27.6 32.2 36.8 Nominal Capacity (Ah) Rated Capacity (Ah) Nominal Voltage (V) 51.2 Voltage Range (V) 46.4~57.6 Rated Current (A) Max Current (A) Operating temperature 0℃~50℃...
  • Page 80 7.2 SPH 3000-6000TL-HUB Specifications Model SPH 3000 SPH 3600 SPH 4000 SPH 4600 SPH 5000 SPH 6000 TL -HUB TL-HUB TL-HUB TL-HUB TL-HUB TL-HUB Specifications Input data (PV) Max. recommended PV 6000W 7200W 8000W 9200W 10000W 12000W power(for module STC) 6000W Max.
  • Page 81 SPH 3000 SPH 3600 SPH 4000 SPH 4600 SPH 5000 SPH 6000 Model TL -HUB TL-HUB TL-HUB TL-HUB TL-HUB TL-HUB Specifications Adjustable power 0.8leading…0.8lagging factor THDI <3% AC connection Single phase EPS output date Rated output 3000VA 3680VA 4000VA 4600VA 5000VA 6000VA apparent power...
  • Page 82 SPH 3000 SPH 3600 SPH 4000 SPH 4600 SPH 5000 SPH 6000 Model TL -HUB TL-HUB TL-HUB TL-HUB TL-HUB TL-HUB Specifications Inverter topology Non-isolated Operating temperature –25°C ... +60°C (-13...+140℉) with derating above 45°C /113℉ range Storage temperature –25°C ... +60°C (-13...+140℉) range Safety level Class I...
  • Page 83 Model SPH 3000 SPH 3600 SPH 4000 SPH 4600 SPH 5000 SPH 6000 TL -HUB TL-HUB TL-HUB TL-HUB TL-HUB TL-HUB Specifications Cooling concept Natural Relative 100% humidity Features PV connection AC connection connector BAT connection connector Display Interfaces: RS485/ USB yes /opt /CAN/WiFi/GPRS /ShineWiLan...
  • Page 84 In case that the SPH inverter becomes faulty, please notify Growatt promptly and provide information about the SPH. To provide you with better support, please have the following information ready: Ÿ...
  • Page 85 AC F Outrange local grid standard 2. Restart the inverter. for more details for 3. Contact Growatt support if the problem the grid frequency persists after restart. 1. Check if the distance between SP-CT and PairingTime Communication fault inverter is within the specified range.
  • Page 86 Please refer to the 1. Restart the inverter. Output High local grid standard 2. Please contact Growatt support if the for disconnection problem persists after restart. time when the output DC current is too high. 1. Check if the battery voltage is within the specified range.
  • Page 87 Error Message Description Suggestion Internal 1. Restart the inverter. Error 411 communication 2. Please contact Growatt support if failed the problem persists after restart. 1. Restart the inverter. Error 417 Sampling error 2. Please contact Growatt support if the problem persists after restart.
  • Page 88 Error message Temperature over Check if the temperature is within the Error 408 range specified range. PV voltage higher Check if the PV input voltage is within PV Voltage High than the the specified range. specification 8.2 Battery Fault List and Troubleshooting Suggestions Error Error Indication...
  • Page 89 Interior CAN Communication Check Can connection between Communicatio loss between two batteries, CAN connection n failure two batteries between Linkin and Linkout. (ALM Light Parallel Communication Check Can connection between Flickers) connection failure between two batteries, CAN connection failure two parallel- between Battery and PCS.
  • Page 90 OSS web, which then notifies the user via e-mail. 8.4.1 Requirements for Remote Communication To enable the remote communication, you need to install a Growatt datalogger to connect to the Internet and upload data to the Growatt monitoring platform OSS.
  • Page 91 8.4.2 Setting up Remote Reporting Once the energy storage system has been successfully added on the OSS, please Ÿ follow steps below: a) Open OSS, select your PV System, and navigate to “Settings”. Figure 8. 1 OSS interface b) Click “Add” under “E-mail Setting” section. Figure 8.
  • Page 92 c) Enter the email address in the “E-mail” field, tick “Receiving Alarms”, and click “Yes”. Figure 8. 3 Set E-mail notifications d) Verify if the e-mail address has been successfully added. Figure 8. 4 E-mail setup succeeded...
  • Page 93 8.4.3 Check Historical Alarms If an inverter error occurs (including the Earth Fault error), the system will automatically send alarm notifications to the e-mail address added in the previous step. Users can also check other historical alarms on the OSS by operating the following steps: a) Open OSS, select the target system and navigate to “Log”.
  • Page 94 Appendix 9 9.1 Other Optional Accessories The following chart lists optional accessories for the inverter. To place orders, you can contact Growatt or your dealer. (P/N is for reference only and subject to change.) Name Description GROWATT P/ N Used for data logging in EU MR00 .0011200...
  • Page 95 Download Manual Shenzhen Growatt New Energy Co., Ltd. 4-13/F, Building A, Sino-German (Europe) Industrial Park, Hangcheng Blvd, Bao'an District, Shenzhen, China +86 755 2747 1942 service@ginverter.com en.growatt.com GR-UM-435-A-00 (PN:044.0124000)