F&F WZE-3-RST Quick Start Manual page 5

Electricity consumption meter, 3-phase, resetable

Advertisement

Number of the meter
The meter is marked with an individual factory number to enable
its unambiguous identification. The marking is indelible (laser
engraving).
Mounting
1. Disconnect power supply.
2. Mount meter on a rail in distribution box.
3. Open terminal covers.
4. Connect the power supply to the terminals 1 (L1 IN), 2 (L2 IN),
3 (L3 IN), 4 (N IN).
5. Connect the circuit to be measured or a single consumer to
the terminals 5 (L1 OUT), 6 (L2 OUT), 7 (L3 OUT), 8 (N OUT).
6. Additional pulse receiver connected to terminals (+) and (–).
The terminals are located under the bottom cover of the me-
ter.
Additional pulse receiver is not required.
7. Put the meter terminals covers.
- 5 -

Advertisement

loading
Need help?

Need help?

Do you have a question about the WZE-3-RST and is the answer not in the manual?

Questions and answers

This manual is also suitable for:

Wze-3