5G mobile Ethernet network. Due to its versatility, the S9600-102XC can be positioned in different parts of the network to perform aggregation, such as in the backhaul to aggregate BBU pooling or even as a Broadband Network Gateway (BNG) within the central office.
1.19 inches (3cm). Therefore, to accommodate the fan and power supply handles, cable routing, a minimum space clearance of 6 inches (15.2cm) is needed at the back and front of the S9600-102XC. A total minimum reserve depth of 36 inches (91.44cm) is required.
S9600-102XC requires 2RU (3.45”/8.8cm) in height, 19” (48.3cm) in width, and need a minimum reserve depth of 36 inches (91.44cm) Thermal requirements S9600-102XC working temperature is 0 to 45°C (32°F to 113°F), airflow direction is front-to-back Installation tools required #2 Philips Screwdriver, 6-AWG yellow-and-green wire stripper, and...
AC power cord (AC version only) 0.71lb (325g) SMB TO BNC Converter Cable 0.04lb (18g) S9600-102XC (W x D x H) 17.16” x 24” x 3.45” (436 x 609.6 x 87.7mm) Dimension PSU (W x D x H) 1.99” x 12.64” x 1.57” (50.5 x 321 x 39.9mm) Fan (W x D x H) 3.2”...
4 Identifying Your System S9600-102XC Overview Figure 4. PSU Overview Power supply unit (PSU) with 1+1 Redundancy. Hot swappable, field replaceable unit (FRU). AC Version: Figure 5. S9600-102XC Hardware Installation Guide | 7...
DC Version: Figure 6. Fan Overview 3+1 Redundant, hot swappable, field replaceable unit (FRU). Figure 7. S9600-102XC Hardware Installation Guide | 8...
Port Overview Port ID Form Factor Maximum Support Distance Support Speed 0 ~ 95 SFP28 Up to 24.85mi(40km) 1/10/25G 96 ~ 101 QSFP28 Up to 49.7mi(80km) 40/100G Figure 8. S9600-102XC Hardware Installation Guide | 9...
Make sure the locking screw of the inner rail is positioned at the front of the chassis. 2.2 After the attachment pins are secured to the inner rail, lock the inner rail to the chassis using two M4 screws (one on each chassis side). S9600-102XC Hardware Installation Guide | 10...
Page 13
4.4 Push the blue release tab on each rail to unlock the rails and slide the chassis all the way into the rack. 4.5 Lock the chassis into place by using the screw on the front of the inner rail. S9600-102XC Hardware Installation Guide | 11...
5. An audible click will be heard when the fan module is installed correctly. The fan module will not go in all the way if it is installed in the wrong direction. Figure 15. S9600-102XC Hardware Installation Guide | 13...
1. Locate the red release tab on the PSU. Then press and hold down the release tab to unlock the PSU. 2. While holding down the red release tab, grip the PSU's handle and firmly pull it out of the power bay. DC Version: AC Version: Figure 17. S9600-102XC Hardware Installation Guide | 14...
Page 17
5. An audible click will be heard when the PSU is installed correctly. The PSU will not go in all the way if it is in the wrong direction. DC Version: AC Version: Figure 17. S9600-102XC Hardware Installation Guide | 15...
3. Insert the exposed grounding wire all the way into the hole of the grounding lug (provided with package contents). 4. Using a crimping tool, firmly secure the grounding wire to the grounding lug. Figure 19. S9600-102XC Hardware Installation Guide | 16...
Page 19
Figure 20. 6. Using 2 M4 screws and 2 washers (provided with the package contents), firmly lock the grounding lug to the designated grounding location on the router. Figure 21. S9600-102XC Hardware Installation Guide | 17...
Also, please ensure that both PSUs have been properly installed before powering up the equipment, as the S9600-102XC is designed to support 1 + 1 power redundancy. 2. Attach the DC power cables to the lugs.
Page 21
Locate the DC power screw-type terminal block located on the PSU. Remove the plastic cover that is protecting the terminal block by pushing from the top or bottom of the cover and flipping open the cover outwards. Secure the one-holed lugs (with the DC power cable S9600-102XC Hardware Installation Guide | 19...
If connected correctly, when turned on, the LED on the PSU will light up with a Green color designating normal operation. AC Version 1. Ensure there is enough power to supply the system. The maximum system power consumption is 751 watts. It is recommended to ensure that S9600-102XC Hardware Installation Guide | 20...
Page 23
Also, please ensure that both PSUs have been properly installed before powering up the equipment, as the S9600-102XC is designed to support 1 + 1 power redundancy. 2. Attach the power cable.
Fan fail: one or more Fans need service No Power Solid Green PSU0 is working normal Blinking Amber PSU0 fail (PSU0 need service) No Power Solid Green PSU1 is working normal Blinking Amber PSU 1 fail (PSU1 need service) S9600-102XC Hardware Installation Guide | 22...
Additional information about fan status can be obtained by the LEDs located on the fan itself. LED Condition Equipment Status No input power Green Fan FRU function normal Amber Fan FRU abnormal, service is required S9600-102XC Hardware Installation Guide | 23...
After the connection is established, a prompt for the username and password displays. Enter the username and password to access the CLI. The username and password should be provided by the Network Operating System (NOS) vendor. S9600-102XC Hardware Installation Guide | 24...
1. Connect one end of a straight-through Ethernet cable to the GNSS unit 2. Connect the other end of the straight-through Ethernet cable to the port marked “TOD” located on the front panel of the router. Figure 31. S9600-102XC Hardware Installation Guide | 25...
The maximum length of the 1PPS coaxial SMB/1PPS Ethernet cable should not be more than 3 meters. Connect an external 1PPS cable with an impedance of 50 ohms to the port labelled “1PPS”. Figure 33. S9600-102XC Hardware Installation Guide | 26...
It is also recommended the cabling be done by a professional who is grounded, such as by wearing an ESD wrist strap. The following the steps below for connecting a transceiver. S9600-102XC Hardware Installation Guide | 27...
Read the following guidelines before installing an active antenna: • When an active antenna is installed, the S9600-102XC can supply up to 5V DC/150mA on the GNSS port. • If any GNSS amplifier, DC-blocked or cascaded splitter is inserted, the GNSS detection function might be affected, resulting in GNSS satellite clock errors.
Warning: This equipment must be grounded. Do not defeat the ground conductor or operate the equipment without correctly grounding the equipment. If there is any uncertainty about the integrity of the equipment's grounding, please contact the electrical inspection authority or a certified electrician. S9600-102XC Hardware Installation Guide | 30...
Page 33
This is a Class A product based on the standard of the Voluntary Control Council for Interference by Information Technology Equipment (VCCI). If this equipment is used in a domestic environment, radio disturbance may arise. When such trouble occurs, the user may be required to take corrective actions. S9600-102XC Hardware Installation Guide | 31...
Page 34
(Type 2, 4, or 4a ports as described in GR-1089) and require isolation from the exposed OSP cabling. The addition of Primary Protectors is not sufficient protection in order to connect these interfaces metallically to an OSP wiring system.” S9600-102XC Hardware Installation Guide | 32...