2. After you locate your rack cabinet, use a 12-mm open-end wrench to lower the
Figure 2. Lowering the rack cabinet leveling feet
3. Place the stabilizer bracket so that the holes in the vertical flange align with the
Figure 3. Securing the stabilizer bracket to the rack cabinet
4. If a UPS came with your cluster, you must install it first in the bottom of the rack.
6
IBM® xSeries 340 HA Cluster: Installation Guide
four leveling pads on the bottom of the rack cabinet until they make firm contact
with the floor.
threaded holes on the bottom-front of the rack cabinet; then, secure the stabilizer
bracket to the rack cabinet with the four screws that come in the box with the
bracket.
Note: If necessary, bolt the bottom of the stabilizer bracket to the floor. Other-
wise, use the bracket plugs to fill the holes in the stabilizer bracket.
Slide the UPS into the bottom of the rack and secure it to the rack with the pro-
vided M6 screws.
Note: The batteries inside of the UPS are disconnected before shipping. See
the documentation that comes with the UPS for instructions on how to con-
nect the batteries before you turn on your UPS or any devices that are
connected to it.