PROCEDURE
1. Be certain the machine is properly connected for the input voltage
being applied.
2. Turn the power switch ON and see that the machine goes through
the Start-up routine and the status light is steady green.
3. Turn the power switch OFF and connect a resistive load across the
output studs and a computer to the ethernet.
4. Perform the Power Wave Verification And Calibration Procedures,
see SVM251.
RETEST AFTER REPAIR
TROUBLESHOOTING AND REPAIR