Plumbing Hook Up
As directed in the International Plumbing Code of the
International Code Council and the Food Code Manual of
the Food and Drug Administration (FDA), this equipment
must be installed with adequate backflow prevention to
comply with federal, state and local codes. For models
installed outside the U.S.A., you must comply with the
applicable Plumbing /Sanitation Code for your area.
The plumbing connection is a 3/8" male flare
fitting located on the lower, left, rear of the
machine as shown.
NOTE: Water pipe connections and fixtures
directly connected to a potable water supply
shall be sized, installed, and maintained in
accordance with federal, state, and local codes.
1. Main water supply shut off valve should be
present between water supply and machine.
2. Place Nylon Gasket (find in separate bag) into
end of water line as shown. (PN 33149.0000)
3. Flush the water line and securely attach it to
the inlet fitting at the rear of the brewer.
4. Turn on the water supply and check for leaks.
Drain Hook Up
1. The drain connect is a barb fitting located at the
back, right leg.
2. The drain hose must be rated to withstand
temperatures of 190˚F (87.8˚C) and higher.
3. Installation of drain hose must be gradually
slopped and routed without any kinks or rise in
the tubing going to the nearest open drain.
4. For Through Counter drain hook up; use the
included 90˚ Elbow Fitting (PN 38553.0001)
to route hose down, through the counter.