far to space the ring so the screws do not interfere with the squirrel cage inside.
See picture 4.
5. Location of correctly spaced self-tap screws.
6. Once the motor is installed inside of the house, in the previously installed
bracket, insert hose tips into the bracket and twist.

Install Hose to Endwall Flange

1. Sandwich Flange Plate (on the inside) and Flat Plate (on the outside) between
the end wall film in line with the mounted fan on the next hoop from the end wall.
Secure with #8 self-tap screws.
2. Gently cut plastic from the hole.
3. Attach the air hose from the motor to the end wall flange and twist.

Double Layer Plastic

Step 4: Installing the Second Layer of Plastic
Install the Inflation Blowers before installing the 2nd layer of greenhouse plastic.
Double-layer greenhouse film is put on exactly like the first layer. The only thing to keep
in mind is the double layer is inflating only from end wall to end wall and hip brace to hip
brace. The spring wire will fit into the end wall hoops that already have the two springs
and two layers that make up the 1st film piece and end wall piece.
Note: When first inflating your double layer start with the baffle wide open and
adjust if necessary.