28.1.4
152
Sudden change in phase current
protection (SCC1)
5.
Measure the time between the change in current and the
SCC1_START (SCC1_TRIP) signal.
6.
Compare the measured time with the set values tHStart and tHTrip.
7.
Repeat item 11-16 for the other two phases.

Completing the test

Continue to test another function or complete the test by setting the test mode off.