8.
Install the access panel.
9.
Install the server into the rack.
10. Connect each power cord to the server.
11. Connect each power cord to the power source.
12. Power up the server.
Installing a secondary full-height riser option
Prerequisites
This option requires a dual processor configuration.
Before installing this option, be sure you have the following:
•
The components included with the hardware option kit
•
Any expansion boards or controllers you plan to install
•
T-10 Torx screwdriver
•
T-15 Torx screwdriver
Procedure
1.
Power down the server.
2.
Remove all power:
a. Disconnect each power cord from the power source.
b. Disconnect each power cord from the server.
3.
Do one of the following:
Hardware options installation