CAUTION: Protect the server from power fluctuations and temporary interruptions with a regulating
uninterruptible power supply. This device protects the hardware from damage caused by power surges
and voltage spikes and keeps the system in operation during a power failure.

Electrical grounding requirements

The server must be grounded properly for proper operation and safety. In the United States, you must install
the equipment in accordance with NFPA 70, National Electric Code Article 250, as well as any local and
regional building codes. In Canada, you must install the equipment in accordance with Canadian Standards
Association, CSA C22.1, Canadian Electrical Code. In all other countries, you must install the equipment in
accordance with any regional or national electrical wiring codes, such as the International Electrotechnical
Commission (IEC) Code 364, parts 1 through 7. Furthermore, you must be sure that all power distribution
devices used in the installation, such as branch wiring and receptacles, are listed or certified grounding-type
devices.
Because of the high ground-leakage currents associated with multiple servers connected to the same power
source, use a PDU that is either permanently wired to the building's branch circuit or includes a
nondetachable cord that is wired to an industrial-style plug. NEMA locking-style plugs or those complying
with IEC 60309 are considered suitable for this purpose. Using common power outlet strips for the server is
not recommended.

Rack warnings and cautions

WARNING: When all components are removed, the server weighs 13.04 - 16.27 kg ( 28.74 - 35.86 lb ).
When all components are installed, the server can weigh up to 13.77 - 16.78 kg ( 30.36 - 37.00 lb ).
Before configuring your rack solution, be sure to check the rack manufacturer weight limits and
specifications. Failure to do so can result in physical injury or damage to the equipment and the facility.
WARNING: The server is heavy. To reduce the risk of personal injury or damage to the equipment, do
the following:
Observe local occupational health and safety requirements and guidelines for manual material
handling.
Get help to lift and stabilize the product during installation or removal, especially when the product is
not fastened to the rails. The server weighs more than 13.04 - 16.27 kg ( 28.74 - 35.86 lb ), so at
least two people must lift the server into the server together. An additional person may be required to
help align the server if the server is installed higher than chest level.
Use caution when installing the server in or removing the server from the server.
Adequately stabilized the server before extending a component outside the server. Extend only one
component at a time. A server may become unstable if more than one component is extended.
Do not stack anything on top of rail-mounted component or use it as a work surface when extended
from the rack.