Cerabar PMP11, PMP21, PMP23
Endress+Hauser
Post-connection check
Is the device or cable undamaged (visual check)?
Are all cable glands installed, securely tightened and leak-tight?
If supply voltage is present, is the device ready for operation and do values appear on the display module?
7.1.5
Commissioning
NOTICE
Risk of injury from the uncontrolled activation of processes!
‣
Ensure that no uncontrolled processes are activated in the system.
Function check
Before commissioning your measuring point, ensure that the post-installation and post-
connection checks have been performed.
• "Post-installation check" checklist
• "Post-connection check" checklist
Configuring the menu items
To configure the menu items, loosen the 4 Phillips screws (1) on the display and remove
the cover.
Key functions:
• A: move down and select the items
• B: move up and select the items
• A+B: select the item to configure or acknowledge the setting
Setting the decimal point
Press the B key until "dP" is displayed.
Press A+B to set the decimal point:
Press B or A for up or down:
Press A+B to quit the setting function and to go to the "dP" menu item.