14-FIRST START-UP

WARNINGS BEFORE IGNITION
GENERAL PRECAUTIONS
Remove all parts that may burn from the brazier and the glass (manual, various adhesive labels or any polystyrene).
Check that the brazier is positioned correctly and rests properly on the base.
The first ignition may not be successful as the feed screw is empty and does not always manage to load the brazier
with the required amount of pellets in time to light the flame.
CLEAR THE FAILED IGNITION ALARM FROM THE STOVE PANEL OR APP.
REMOVE THE PELLETS LEFT IN THE BRAZIER AND REPEAT THE IGNITION. (SEE "SAFETY DEVICES/ALARMS" PARAGRAPH)
If after repeated attempts, the flame fails to ignite, despite a regular flow of pellets, check the correct positioning of the brazier, which
must rest snugly against the slots. If no anomaly is found during this inspection, there may be a problem with the product components
or installation may not be correct.
REMOVE THE PELLETS FROM THE BRAZIER AND CONTACT AN AUTHORISED TECHNICIAN.
Do not touch the stove during the first lighting, as it is during this phase that the paint sets. If you touch the paint,
you may expose the steel surface.
It is good practice to ensure effective ventilation in the room during the initial start-up, as the stove will emit some
smoke and smell of paint.
If necessary, touch up the paint with the spray can of the specific colour.
Do not stand close to the stove and, as mentioned, air the room. The smoke and smell of paint will disappear after about an hour of
operation, however, they are not harmful in any case.
The product will be subject to expansion and contraction during the start-up and cooling stages, therefore slight
creaking noises may be heard. This is absolutely normal as the structure is made of laminated steel and must not be
considered a defect.
Upon first ignition, for the first pellet tank, it is recommended to start the stove at maximum power so that the structure and the smell
of the paint settle more quickly.
It is recommended to install the ceramic or Serpentine stone cladding after the first successful ignition.
DO NOT EXPECT HEATING EFFICIENCY IMMEDIATELY!!!