Installing The Bottom-Support Rails - Cisco Nexus 9508 Hardware Installation Manual

Aci-mode switch
Hide thumbs Also See for Nexus 9508:
Table of Contents

Advertisement

Installing a Chassis
• For three modules, they must be in slots FM 2, FM 4, and FM 6.
• For four modules, they must be in slots FM 2, FM 3, FM 4, and FM 6.
• For five modules, they must be in slots FM 2, FM 3, FM 4, FM 5, and FM 6.
• For six modules, they are in slots FM 1, FM 2, FM 3, FM 4, FM 5, and FM 6.
• Fan trays (3)
• Power supplies (1 to 8)
• 3-kW AC power supply (N9K-PAC-3000W-B)
• 3-kW Universal AC/DC power supply (N9K-PUV-3000W-B)
• 3.15-kW Dual Input Universal AC/DC power supply (N9K-PUV2-3000W-B)
• 3-kW DC power supply (N9K-PDC-3000W-B)
• Rack Mount kit
• Rack mount kit for the Cisco Nexus 9508 (N9K-C9500-RMK) chassis
• Bottom-support rails (2)
• M6 mounting screws (20)
• 10-32 mounting screws (20)
• 12-24 mounting screws (20)
• Switch accessory kit (N9K-ACC-KIT)
Step 2
Check the contents of each box for damage.
Step 3
If you notice any discrepancies or damage, send the following information to your customer service representative by
email:
• Invoice number of the shipper, see the packing slip.
• Model and serial number of the missing or damaged unit
• Description of the problem and how it affects the installation.
• Photos of the damage to external packaging, internal packaging, and product

Installing the Bottom-Support Rails

The bottom-support rails support the weight of the switch chassis in the rack or cabinet. To maximize the
stability of the rack, you must attach these rails at the lowest possible rack unit (RU).
Cisco Nexus 9508 ACI-Mode Switch Hardware Installation Guide

Installing the Bottom-Support Rails

21