Installation Review : A Checklist - Vogt TUBE-ICE 03TB Service Manual

Table of Contents

Advertisement

03TA Service Manual
Installation Review: A Checklist. Make a visual check to be sure these steps have been taken
BEFORE continuing.
CHECK: ____ PRIOR TO OPENING VALVES, check all joints for leaks which may have
developed during shipment.
(NOTE: the machine was shipped with a positive pressure of 20-25 PSIG, verify on
the freezer pressure gage.)
CHECK: ____ All refrigerant piping, water supply and drain connections for conformity to
requirements stipulated in this manual and properly connected to inlets and outlets.
CHECK: ____ Electrical supply for proper size of fuses and for compliance to local and national
codes. See the machine nameplate for minimum circuit ampacity and maximum fuse
size.
CHECK: ____ All field installed equipment (augers, conveyors, cooling towers, bin level controls,
etc.) for proper installation.
CHECK: ____The applicable portion of the warranty registration/start-up report for proper
completion.
CHECK: ____ Cutter gear reducer oil level oil should run out of side pipe plug when removed.
CHECK: ____ The water distributors at top of freezer to make sure they are all in position
The compressor crankcase heater should be energized for a minimum of
!
IMPORTANT
Be sure to follow the wiring schematic and electrical
specification table when incorporating overloads.
This is necessary to provide proper protection
® ® ® ®
for the Tube-Ice
machine and its component parts.
!
IMPORTANT
!
Two (2) hours before attempting to start the compressor.
!
!
!
CAUTION
!
CAUTION
!
INSTALLING YOUR TUBE-ICE
3-21
®
MACHINE

Advertisement

Table of Contents
loading

This manual is also suitable for:

He60P112f

Table of Contents