Test Run; Collective Operation On/Off - Mitsubishi Electric Trane TE-200A Installation Manual

Air conditioning control system
Hide thumbs Also See for Trane TE-200A:
Table of Contents

Advertisement

8. Test run

8-1. Collective operation ON/OFF

Confirm that the group settings and interlock settings are complete before performing a test run.
It may take approximately five minutes from power on until the local remote controllers become operable.
Refer to the indoor unit Installation Manual for details about a test run.
Test run procedure
(1) Turn on the power to the TE-200 and all units.
(2) After the message [Please wait...] disappears, touch the [Unit info. 2] tab in the [Initial Settings] menu. Set the [Test
run] setting to [Use] to show the [Test Run] button on the operation settings screen under the [Monitor/Operation]
menu. Touch the [Test Run] button on the operation settings window. The group of units will start an operation.
(3) Check for the proper operation of each unit during the test run (e.g., check to see if cold (or warm) air comes out
of the supply air outlet on each indoor unit).
(4) After confirming that all units are operating properly, stop the units either from TE-200 or from the local remote
controllers.
WT09302X01
24

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Trane te-50a

Table of Contents