Installation Instructions

Verifying Proper Operation

1.
Before starting the test procedure, turn off all burners, and see that all burner components and
grates are properly positioned.
2. Open the gas-supply valve, and check for gas leaks.
3. Turn on power to the range at the circuit breaker or fuse box.
4. Use the oven display to set user preferences and wireless network settings.
5. On the display, tap MENU > BAKE. (The default bake temperature should appear.)
6. Tap Start. In 3 minutes, open the door to see that the oven chamber is heating. (The display
should show BAKE and the preheating temperature.)
7.
Tap OFF.
8. Push a knob in, and turn it counterclockwise to HIGH. (Within 4 seconds,
ignition occurs, and the igniter stops sparking. If ignition does not occur
as expected, turn off the knob, wait 5 minutes for the gas to dissipate,
then retry the test.
9. After ignition, turn the control knob from HIGH to LOW while watching
the flame height. If the range is installed properly, the flame is steady
and quiet with a sharp, blue inner cone that varies in length depending
on the burner size.
10. Turn the control knob OFF.
11. Repeat the ignition test for the remaining burners.
If the range does not operate properly:
1. Verify that power and gas are supplied to the range.
2. Check the electrical connections and gas supply to verify proper installation.
3. Repeat the above bake test and burner-ignition test.
4. If the range still does not work, contact Dacor Customer Assurance: (800) 793-0093 x2813. Be
ready with the model/serial numbers. (See the data label, left-side door trim.)
Do not try to repair the range yourself. Dacor is not responsible for the cost of correcting
problems caused by a faulty installation.

Removing and Reinstalling the Range

Removing the Range for Service
Close the gas-supply valve.
1.
Turn off power to the range at the circuit breaker or fuse box.
2.
Pull the range out from the wall
3.
Reinstalling the Range After Service
1. Push the range into position, engaging the anti-tip bracket.
2. Turn on power to the range at the circuit breaker or fuse box.
3. Open the gas-supply valve.