The figure below provides the internal wiring implementation of the fan control parts shown above.
Figure 16. Battery cooling fan control wiring diagram
Both power to the G5 Stack Switchgear and the fans are both expected to be de-
energized before installation; this usually involves turning off each respective
breaker at a panel.
4.3.3.5. Connect control to General Purpose Input/Output (GPIO) cable
If you are building your own cables, please refer to the pin out for this connector in
I/O
Connector.
Connect the I/O cable to the connector on the front of the G5 Stack Switchgear.
4.3.3.6. Connect Ethernet cable to external computer