During all stages of the installation, appropriate Personal Protective Equipment (PPE)
must be worn. This is especially critical when working with live voltages.
To complete the installation of the G5 Stack Switchgear, the following is required:
Mounting Brackets
Brackets for shelf mounting are included. Optionally, you can request Front-securing Brackets for
19" Rack mounting if appropriate for your application.
Cables
To connect your G5 Stack Switchgear you will require the following cables:
1x Power Cable for either AC or DC power.
1x Voltage and Thermistor cable to connect to the G5 Cell Interface
1x Ethernet cable for communication with the G5 Cell Interface
These cables are available for purchase as a kit.
The instructions below are for applications using cable harnesses purchased from Nuvation Energy. To
build custom cables, refer to
specifications.
Tools and Materials
You will need the following tools and materials to complete your G5 Stack Switchgear installation:
M13 and M17 wrench
Torque wrench with range 60-130 inch pounds
Fasteners and tools for attaching the brackets to the end desired surface.
G5 Cell Tap Checker - To test cable connectivity. Contact
purchase
Document ID: NE-DS-011
Nuvation Energy G5 High-Voltage BMS - NUVG5 Product Manual
G5 Stack Switchgear Connectors
18
for connector pin-out and
support@nuvationenergy.com
Rev 1.0, 2023-05-19
to
G5 Faraday

Advertisement

Table of Contents
loading

Table of Contents