Installing the Outer Rails onto the Rack

1. Press upward on the locking tab at the rear end of the middle rail.
2. Push the middle rail back into the outer rail.
3. Hang the hooks on the front of the outer rail onto the square holes on the front of the
rack. If desired, use screws to secure the outer rails to the rack.
4. Pull out the rear of the outer rail, adjusting the length until it just fits within the posts of
the rack.
5. Hang the hooks of the rear section of the outer rail onto the square holes on the rear of
the rack. Take care that the proper holes are used so the rails are level. If desired, use
screws to secure the rear of the outer rail to the rear of the rack.
1
2
Figure 2-4. Installing the Outer Rails to the Rack
Note: Figure is for illustrative purposes only. Always install servers at the bottom of a rack first.
Stability hazard. The rack stabilizing mechanism must be in place, or the rack must
be bolted to the floor before you slide the unit out for servicing. Failure to stabilize the
rack can cause the rack to tip over.
L-min=676.00(26.61")(outer rail)
21D01
3
27
Chapter 2: Server Installation
4

Advertisement

Table of Contents
loading

This manual is also suitable for:

Sys-superserver 221p-c9rt

Table of Contents