Section 9
Testing IED operation
outputs on multiple I/O boards at the same time. It is also possible to abort this operation (described in
step 6 below) and to
1.
Right click on the IED in the plant structure and select Signal Monitoring.
2.
Click on the List View tab.
3.
Click Forcing Session in the menu IED/Start Forcing.
IEC15000023 V1 EN-US
4.
Click Start editing signal value for forcing on the tool bar.
IEC15000024 V1 EN-US
The Signal Monitoring menu changes and indicates the forcing values that can be edited.
IEC15000025 V1 EN-US
5.
Select and edit the values.
6.
Click Acknowledge and send.
IEC15000026 V1 EN-US
66
undo all
forcing.
© 2017 - 2022 Hitachi Energy. All rights reserved
1MRK 505 372-UUS Rev. K
Busbar protection REB670
Commissioning manual

Advertisement

Table of Contents
loading

This manual is also suitable for:

Relion reb670

Table of Contents