5| Electrical connection
5.6 Function test of the trigger unit INT69 G
Before commissioning, after troubleshooting or making changes to the control power circuit, check
the functionality of the trigger unit. Perform this check using a continuity tester or gauge.
Gauge state
1.
Deactivated state
2.
INT69 G switch-on
3.
Remove PTC connector
4.
Insert PTC connector
5.
Reset after mains on
5.7 Start unloader
To avoid current peaks during the starting phase we recommend using the GEA Bock-ESS soft
starting device (Electronic Soft Start). Refer to "Accessories" for further information.
Relay position
11-12
11-14
11-12
11-12
11-14
Relay position INT69 G
B2 12 14 11
Fig. 19
D
GB
F
E
I
Ru
19